
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
September 27, 2011
Page 2 of 3
Phillips Construction Services
Staff analyzed the engineers estimate of $304,274 and found the following items either were not
priced appropriately for the final scope or were not accounted for in the final estimate:
The customer service kiosks require customization and as a result are more expensive
than estimated as off-the-shelf. The estimate was completed before design documents
were final.
The kiosks, security gate assemblies and other access control systems are long lead items.
Given the aggressive schedule the estimate did not consider the potential risk.
The estimate did not consider costs associated with being under the 1999 Project Labor
Agreement or higher contractor mark-ups typical of a small project.
The engineer’s estimate did not take into account any costs that may have been included
related to the new Port Small Contractor & Supplier (SCS) initiative. The contract had a
6% requirement for SCS firms.
The successful contractor will be required to comply with the current RCF contractor’s
safety and security requirements and limited access, laydown and on-site employee
parking requirements that may have been perceived as a risk not considered in the
estimate.
Based on the reasons stated above, the three lower bidders were within 10.5% of each other,
which appears representative of the marketplace, and because all four were above the engineer’s
estimate, Port staff believes the low bid represents a fair and reasonable price.
BACKGROUND & PROJECT SCOPE OF WORK:
The RCF program provides a long-term solution for rental car company operations at the Airport
by centralizing all rental car operations in a single facility located at the north end of the Airport.
It will provide operational space for up to three (3) small operator rental car companies to
operate at the RCF. As defined the Consolidated Rental Car Facility Lease Agreement: “Small
Operator” shall generally mean and refer to an Operator whose market share constitutes less than
two percent (2%) of the overall Market Share for rental cars at the Airport and which operates
from the Small Operator Area.
The project is designed to accommodate three (3) Small Operators in the new RCF. During the
design of the RCF, it was not known how many Small Operators would participate or how large
an area would be required to accommodate them. During the contract negotiations with Turner
Construction, an area was identified and shown within their contract to accommodate any future
Small Operators. Design and construction of this SOAwas not in Turner’s contract. Aviation