COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
September 20, 2011
Page 3 of 7
Connecting to existing building structures to provide structural support for equipment and
piping.
The Contract addresses the majority of these issues; however, some were not identified until
means of access was discussed with the contractor and the contractor submitted detailed shop
and installation drawings.
Total estimated cost of change orders is $4,050,000. Current construction contract contingency
is $2,450,000. We are requesting authorization of $1,600,000 for the difference between our total
estimate of change orders and the current contingency, so that the contingency is sufficient for all
currently anticipated change orders. Staff will return to Commission at a later date for specific
construction contract change order authorizations when required by Resolution 3605.
The change orders include the following elements:
Access challenges--$600,000 – The majority of this increase is for access to the North
and South Satellite utility tunnels, where access limitations do not allow pipe lengths as
long as assumed in the Engineers Estimate.
Field conditions; i.e., Piping conflicts and interferences--$1,500,000 - During the
preparation of detailed drawings, the contractor identified additional interferences and
conflicts with existing utilities and equipment.
Building and Electrical Code required revisions--$450,000 - To qualify the project for the
VALE FAA Grant, the project was bid before the building permit was approved. The
permit review generated some changes to the project requirements due to Code and to
correct electrical power issues.
Potential Contract disputes--$450,000 - During the process of reviewing contract required
submittals it has become apparent that the Port and Contractor disagree about some areas
of work. These issues will be resolved through contract negotiations
Contract Scope changes --$700,000 – There have been changes to airport facilities and to
Port technical requirements since contract documents were completed and contract was
awarded.
Miscellaneous change orders for scope omissions and field conditions discovered during
construction--$350,000 Additionally, Port Construction Services (PCS) is supporting this project
by relocating tenants and removing and reinstalling covers and panels for piping installation. The
original project estimate for this work was $331,000. To support alternate routing of concourse
piping additional work is required. The revised cost of this work is estimated to cost $750,000,
an increase of $419,000.
Additional design team support is needed for project changes and unanticipated field conditions.
This increased cost is estimated to be $400,000 ($50,000 for scope changes and $350,000 for
additional construction support. The initial contract with Stantec Engineers was for $2,011,564
($ 1,608,911 for design and $402,653 for construction support). Total current contract value
following amendments to date is $2,579,257 ($1,176, 591 for design and $402,666 for
construction support). Staff is negotiating the fee with Stantec and will finalize the amendment
for execution once this request is approved. Pending negotiations, this will increase total contract
value to $3,129,257. The Period of Performance for the Service Agreement will not change.