
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
September 16, 2011
Page 2 of 4
The total amount of the panel replacement change for design, procurement and installation of the
new electrical panels combined is currently estimated at $1,000,000.
BACKGROUND:
The potential for replacement of the electrical panels was identified by the Port in the original
Request for Proposals for this D-B contract. The existing power distribution system (panels,
conduits, and wiring) is over 20 years old. The electrical demands required to support the 44
new escalators are determined based on the D-B bidder design. The Port determined through
results of a thorough design process and review by the Port’s Proactive Electrical Systems Team
(PEST) committee that the existing electrical panels are insufficient and must be replaced.
Change Order #5 was issued for the not-to-exceed amount of $97,000 to initiate the design of the
panel replacement and allow for early procurement of the panels to avoid schedule impacts to the
project. At that time, it was anticipated the final design and subsequent pricing for the
installation of the new panels would be complete and the final cost negotiated before the work
was scheduled to begin in mid-to-late September 2011. The project was designed in four phases
and the added scope of work has been incorporated in the 90% design development. Three
phases have now been permitted, and the permitting of the fourth phase is nearing completion.
On August 26, 2011, the Contractor provided their final estimate of the costs for installation of
the panels in the amount of $900,000 and notified the Port that the new panel replacement work
is scheduled to begin mid-September. There is not enough time to generate an independent cost
estimate and negotiate the final cost before work is slated to begin in mid-September.
After discussion with the Assistant Director of Engineering – Construction Services and the
Director of Capital Development Division, the decision was made to issue an interim not-to-
exceed change order to allow the contractor to start work while the Port conducted its
independent estimate and negotiated the final costs for this work to avoid schedule delays. This
Change Order (#20) was issued on September 9, 2011.
A final reconciliation change order will be issued after the final cost have been established. Staff
does not expect the final amount to exceed the Contractor estimate of $900,000.
FINANCIAL ANALYSIS:
Funds to pay for this change order are part of the project contingency funds that were included in
the previously approved authorization of $45,000,000. No additional project funds are being
requested as a result of this change order.