AVIATION PROJECT SUMMARY, Cont.
• One project is forecasting an overrun:
– Central Plant Pre-Con Air ($3,525,000) – Overrun due to
increased design cost, unbudgeted RMM, and additional change
orders and associated soft costs (IC Approval 8/3/11).
• Three projects are under budget:
– Runway 16L/34R Reconstruction (~$200,000) – The project is in
closeout and will be returning savings.
– Connect C1 to C88 BHS (~$300,000) – The project is in closeout
and will be returning savings.
– Third Runway Residential Acquisition (~$300,000) – The project
is in closeout and will be returning savings.