ITEM NO. DATE OF MEETING 7b supp . September 12, 2011 . Airline Realignment Program Commission Briefing for Seattle-Tacoma International Airport 1 Agenda • Airline Industry Changes Drive Airline Moves • Airline Moves and Schedule • Realignment Program Elements: o Realignment Capital Projects $32.7 million o Linked Capital Projects $70+ million o Expense Projects $20-25 million Total Program: $122-130 million Page 2 Airline Industry Changes The U.S. airline industry continues to face evolutionary changes and consolidations. At Seattle-Tacoma International Airport: • Several airlines have stated desire to relocate and/or consolidate facilities • Delta merged with Northwest and consolidated on the South Satellite as the first step in consolidations. Now United and Continental are merging along with Southwest and AirTran. • Alaska Air Group plans to consolidate their operations to the North Satellite and Concourse C • The Airport has exercised the provision for a one-time airline reallocation as part of the Airline Signatory Lease & Operating Agreement (SLOA) with a notice of intent issued on December 9, 2010 • Airlines directly impacted by this realignment include: AirTran, Frontier, jetBlue, Hawaiian, American, Virgin America, Continental, United, and Alaska Air Group Page 3 Airline Realignment Scope Page 4 Airline Move Schedule Late 2011 • AirTran relocates • Continental ticket counter moves to United Mid 2012 • Virgin America ticket counter moves Mid 2013 • Frontier relocates • jetBlue relocates • American relocates Late 2013 • Virgin America gates relocate • Hawaiian relocates • United/Continental relocates • North Satellite and Concourse C renovation begins Page 5 Airline Realignment Capital Projects Authorized Projects Authorized Amt Concourse D Common Use Exp'n $ 4,250,000 Passenger Loading Bridges $ 6,700,000 Baggage Modifications $ 1,731,000 Exterior Gate Improvements $ 499,000 Airport Signage $ 238,000 Total: $13,418,000 Projects Remaining to be Authorized Misc. Building Improvements CUSE at Ticket Counters, Gates Est Amt to Authorize $ 560,000 $ 476,000 Total: $1,036,000 Date Remaining Authorized Amt to Auth Jan-25-11 0 Feb-22-11 $ 8,150,000 Mar-01-11 $ 3,604,000 Jun-14-11 $ 2,151,000 Jun-14-11 $ 408,000 Total: $14,313,000 Est Date to Authorize N/A Nov 2011 Sept 2011 Dec 2011 Jan 2012 Est Date to Remaining Authorize Amt to Auth Dec-06-11 $ 2,061,000* Jan 2012 $ 1,895,000 Total: $ 3,956,000 Est Date to Auth Nov 2011 Aug 2012 Estimate Grand Total of all Authorizations and Remaining to Authorize: $ 32,723,000* * Anticipate a future budget increase Page 6 Related Projects Linked Capital Projects $70+ million North Satellite Improvements including Seismic, HVAC, club structure Concourse C Improvements North Checkpoint Reconfiguration Estimated cost $70+ million Expense Projects $20-25 million Tenant improvements Continued expenses incurred for the duration of the program into 2014 The current estimate for tenant improvements is approximately $20,000,000 to $25,000,000 and will be finalized as individual airline agreements are reached Future Capital Projects North Satellite Expansion, ticket counter reconfigurations, technology improvements Page 7 • Questions? Page 8