COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
September 2, 2011
Page 2 of 2
BRIEFING OUTLINE:
1. Airline Industry Changes
2. Airline Realignment Scope
3. Airline Move Schedule
4. Airline Realignment Capital Projects
5. Related Projects
OTHER DOCUMENTS ASSOCIATED WITH THIS BRIEFING:
Airline Realignment Program PowerPoint presentation
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS:
On June 14, 2011, the Port Commission authorized 1) design of the Airport Signage –
Airline Realignment project at Seattle-Tacoma International Airport (Airport). This
authorization is for $238,000 of a total project cost of $646,000, and 2) execute a
professional services Indefinite Delivery Indefinite Quantity contract for signage design
services totaling $400,000 for four (4) years in support of upcoming capital improvement
projects, including the Airport Signage Airline Realignment project at the Airport (CIP
#C800474).
On June 14, 2011, the Port Commission authorized Exterior Gate Improvements – Airline
Realignment at Seattle-Tacoma International Airport. This authorization is for $499,000
out of a total project estimated cost of $2,650,000 (CIP #C800472).
On March 1, 2011, the Port Commission authorized design and some construction of the
Baggage Handling System (BHS) Improvements - C22 BHS connection to C1/C1-MK1
Replacement /TC3 Replacement (C800382) in the amount of $1,731,000.
On February 22, 2011, the Port Commission authorized design and some construction for
the Passenger Loading Bridge Replacement Project - Airline Realignment (C800467) in
the amount of $6,700,000.
On February 22, 2011, the Port Commission authorized Planning for Terminal
Realignment in the amount of $713,000.
On January 25, 2011, the Port Commission authorized design and construction of the
Concourse D Common Use Expansion Project (C800455) in the amount of $4,250,000.
Commission was also briefed on the Airline Realignment Program as part of this item.
On June 8, 2010, the Port Commission authorized execution of an IDIQ contract for the
Terminal Development Strategy Campus Planning Services IDIQ in the amount of
$1,300,000.