
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
August 11, 2011
Page 4 of 4
be constructed. The alternative of further delaying demolition of the building or to not demolish
the building would result in the Port not complying with FAA safety regulations. Neither of
these alternatives is recommended. The recommendation is to proceed with the demolition
project as currently scheduled in order to fulfill the Port’s commitment to FAA and comply with
FAA safety regulations.
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST:
Attachment A – map and photo showing proximity of demolition project and relation to the
airport and runways.
PREVIOUS COMMISSION ACTION:
On August 1, 1996, the Commission adopted Port Resolution No. 3212, as Amended, approving
the Master Plan Update for Airport, including development of a new dependent air carrier
runway, and authorizing initial development work for the Runway project.
On May 27, 1997, the Commission authorized $587,362,000 for completion of the Runway
project to be completed by 2004.
On June 22, 1999, the Commission authorized an additional $186,000,000, increasing the total
authorization to $773,362,000. At that time, it was estimated permitting would be finalized by
December 1999 and the Runway project would be complete by fall 2006.
On June 24, 2003, the Commission was briefed on additional costs from delays, permit
conditions, market conditions, scope of project, and FAA requirements. At that time, the
Runway project was scheduled to be completed at the end of 2008.
On October 11, 2005, the Commission authorized an additional $125,000,000 increasing the total
authorization to $898,362,000.
On September 26,
2006, the Commission authorized an additional $219,594,000 increasing the
total authorization to $1,128,956,000.