
Page 4 of 6
Approximately 30 construction workers on site daily.
Milestones Accomplished this Month
Bus Maintenance Building (BMF) and Bus Wash Facility (BWF) tilt-up panel erection is complete.
The BWF concrete plank roof structure is installed and structural steel erection has begun at the BMF
building.
Offsite utility work nears completion at S 194
th
St, and off-site bioswales (adjacent to Tyee Golf
Course) will be punch-listed this month.
Permanent tie-ins to Highline Water District water main are complete.
Puget Sound Energy has completed most of their cut-over work to provide permanent power via the
new “backbone” ductbank on S 194th St.
Work In Progress
BMF Building structural steel erection and welding of tilt-up panels is underway. Interior rough-in
work is limited by wall panel bracing, to be removed when joists & deck are in place & welded.
Sacrificial slabs used for casting tilt-up panels have been removed to facilitate grading & curb/gutter
work at upper and lower site paving/parking areas.
Sewer tie-ins (Midway Sewer District) are pending. Contractor has begun installation and cabling for
electrical switchgear and main distribution panels.
Foundation work is complete with under slab conduits/control circuit pathways at CNG nearly
complete. Contractor has begun pre-fabrication off site for CNG system process piping.
Sod placed at Tyee Golf Course is being watered and maintained by the Contractor to assure viability
of turf. Change order related to a drainage structure has been issued, and revision will not impact
tenant (golf course) operations.
Operation and maintenance costs of TESC and Chitosan Enhanced Filtration System (CEFS)
installations remain low due to mild weather. Budget for environmental elements is tracking within
budget forecasts.
As utility excavation operations near completion, costs for management/disposal of unsuitable soils
have decreased significantly.
Cost Status Summary
Summary: Change Orders: 7 executed, 15 change proposals in review.
Design
RCF: 46 Design Change Notices (DCN’s) have been issued. There are six additional design changes
that will be incorporated into future DCN or Construction Bulletins (CB’s). Approximately 2,200
contractors Request for Information (RFI) have been submitted, of which 2,015 are closed.
Main Terminal Improvements (MTI): Awarding contract to Skanska USA Building, Inc. in underway.
Must be awarded by July 29 to meet schedule. The project will carry $188,000 in construction
contingency, which is 25% of the contract value and higher than normal due to the following
risks: small project, extensive coordination with operations for traffic on lower drive and
safety with the traveling public, unforeseen RMM with sign installation, a contractor not
familiar with the Port’s procedures, and contingency to add or modify signs after completion
of the project.
Small operator area bid documents being finalized for advertisement in early mid August 2011.