PORT OF SEATTLE
MEMORANDUM
DATE: July 15, 2011
TO: Tay Yoshitani, Chief Executive Officer
FROM: Ralph Graves, Managing Director, Capital Development
SUBJECT: Consolidated Rental Car Facility Project Contract MC-0315405
Extension to Contract Completion Date
Amount of This Request: $0 Total Project Cost: $232,002,604.00
Source of Funds: RCF Project Contingency. No additional funds required.
Est. State and Local Taxes: $21,423,533.00 of Total Project Cost Jobs Created: None
ACTION REQUESTED:
Request authorization for the Chief Executive Officer to issue a change order for the
Consolidated Rental Car Facility (RCF) project to extend the completion date by an amount not
to exceed 80 calendar days. Although the Port has received a claim for additional costs related to
schedule delay, this extension would specifically not, at this time, be compensable to the general
contractor/construction manager or any subcontractors.
SYNOPSIS:
The schedule milestone for permanent power-on has slipped from May 6, 2011, to the currently
projected date of July 25, 2011, an 80 calendar day delay. The 80-day extension will not affect
the currently scheduled opening of the RCF. Although the general contractor/construction
manager (GC/CM) has yet to submit a contractually required schedule analysis to demonstrate
that the Port was responsible for this delay, the Port staff believes it may, at least in part, be
responsible for the delay to energizing the electrical equipment. To keep the project moving and
to avoid claims for constructive acceleration, the project staff seeks authorization to issue a
change order extending the required contract completion date 80 calendar days.