
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
July 20, 2011
Page 2 of 6
The scope of work associated with the advance work includes the design of temporary measures
needed to mitigate airline impacts due to anticipated gate closures. Closure of gates may be
required by the construction of the project and may cause reassignment of domestic and
international flights on multiple concourses. Advance work to mitigate these impacts may be
required to allow the major construction to occur during the 2012 construction season without
delay. The temporary measures may include infrastructure modification to existing gates,
signage, and other items to accommodate airline gate reassignments. Budget for this advance
work is in this request and is estimated to be less than $300,000. Advance work may include the
use of Port Crews, consulting services, small works contractors, and/or pre-purchasing some
materials and equipment related to the temporary measures.
BACKGROUND:
Airport staff has been and is continuing to conduct visual surveys of the non-runway pavement
on the airfield to determine which pavement needs replacing and in what sequence. The extent
of the panel and joint seal replacement in 2012 will be based upon this ongoing monitoring. The
concrete and joint seal work must occur in a phased sequence, to minimize impacts to the airlines
and the airport patrons. Airport staff has identified multiple locations on taxiways, taxilanes, and
ramp areas for replacement, due to the deteriorating condition of the pavement, which is at the
end of its useful life. The proposed work in 2012 will focus on replacing pavement as well as
associated utilities in a number of locations on the AOA.
Typical degradation of the concrete is occurring. Joint seal in the area has also degraded and in
some cases is nonexistent.
This project is part of a multi-year program to replace some of the worst pavement and joint seal
on the airfield. The project will generally replace the most critical pavement first, but will
include other pavement sections when it makes sense. The criticality and order of the pavement
replacement may change over time, based on pavement deterioration, operational impacts, and
available budget. The total 2012 project cost will be developed when the scope of panel, joint
seal and associated items replacement, impact to taxilanes and taxiways, and phased sequencing
have been determined during the design phase. The overall program amount is $30.8 million, of
which $6,629,000 has been previously authorized for panel and joint seal replacement
PROJECT JUSTIFICATION:
In areas around the AOA, the age of the existing concrete is resulting in cracked and damaged
panels. There are areas of pavement throughout the AOA that need to be replaced. Concrete
debris resulting from the deteriorating pavement can become a hazard for aircraft and personnel.
This project may displace airline operations at various gates located throughout the airport as
well as taxiway and taxilane configurations. Advance work, internal and external to the
terminals, may be necessary to facilitate airline temporary relocations.