
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
July 19, 2011
Page 2 of 5
BACKGROUND
Runway 16C/34C was constructed of concrete in 1969, with a 20-year design life. The Airport
began a Runway Improvement Program in 1993, which was designed to rehabilitate and extend
the useful life of the runway. More than 400 concrete panels have been replaced since the
beginning of the program. This project, a continuation of the overall Runway Improvement
Program, will replace additional concrete panels where the useful life of the surface panels has
been exceeded.
Typical degradation of the runway is occurring, such as cracking, spalling, and faulting. Cracks
and spalls result in Foreign Object Debris (FOD), which can cause aircraft damage. Faulting
results in a rough ride, but is also indicative of further pavement and subgrade deterioration.
A previous project replaced failing concrete surface panels on Runway 16C/34C during the 2010
construction season. It was noted in the February 9, 2010 request for authorization that, “If it is
necessary to ensure continued operational safety, staff will return to Commission prior to the
reconstruction in 2016, to request additional panel replacement funds.” Since there were savings
from funds previously authorized and a further need for the replacement of surface panels
evolved, this request is to extend the use of those funds to prepare contract documents for a
construction contract to be advertised and constructed in 2012 for additional surface panel
replacement on runway 16C/34C. The replacement of panels on runway 16C/34C is planned to
be part of a single contract that includes the replacement of panels on non-runway surfaces (i.e.,
taxi-ways, taxi-lanes, ramp areas).
Funds were previously authorized for the design, advertisement, and execution for a 2010
surface panel replacement on runway 16C/34C in the amount of $5,650,000. Of that amount,
$2,769,262 has been expended and $1,480,738 has been returned as savings leaving an
unexpended and previously authorized amount of $1,400,000. Up to $200,000 of this amount
will be used for design with the remaining $1,200,000 reserved for the 2012 construction
contract. A request for authority to advertise the construction contract will be brought to the
Commission in early 2012. There are currently four panels on runway 16C/34C identified for
replacement and another twelve that are being monitored. Given that pavement distress will
continue to occur between now and 2012, additional panels will likely be added. Staff believes
that even should a significant accelerated deterioration occur, the $1.4 million for the design and
construction should be sufficient to cover the scope of panel replacement and there may be
possible future savings available to return after the project is complete.
Design would begin in the third quarter 2011 and advertisement would occur no later than the
spring of 2012 so any pavement distress that will have occurred over the winter is identified and
included in the contract. Runway 16C/34C is scheduled to be replaced in 2016 and therefore
2012 is the last year that the replacement of those distressed panels can be capitalized.
PROJECT JUSTIFICATION:
Project Statement:
Perform Runway 16C/34C panel replacement in 2012, for a cost not to exceed $1,400,000 using
previously authorized funds.