
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
July 18, 2011
Page 2 of 6
BACKGROUND:
While minor leaks can be repaired with increased maintenance, the major concern is if large
sections of the roof membrane are damaged during wind storms. Should this occur, the building
and contents would be exposed to the elements disrupting tenant operations and requiring
emergency repairs. As the roof ages, the roof membrane will continue to deteriorate increasing
the likelihood of a major failure. With the building located on a pier, the risk of damage due to
higher open-water wind exposure also increases.
Additionally, the white coating applied to the black membrane has failed in many areas on the
roof. While the failure of the coating does not affect the waterproof integrity of the system, it
does increase the thermal adsorption of the building. Replacing the reflective coating with a new
roofing system will restore the building to the initial energy efficiency.
This project will remove and replace the existing roof membrane and related roofing elements.
This authorization request of $190,000 is for the design development phase of the project. The
design is scheduled to be completed in March 2012. During the design phase, different roofing
system alternatives will be evaluated to determine which system has lowest cost of ownership.
The roofing alternatives include: membrane, built-up and metal with design lives ranging from
20 to upwards of 45 years.
The planning level estimated cost range of the project, including future construction
authorizations is between $1,864,000 and $ 2,445,000. The total estimated cost of the project
has increased from the $1.2 million shown in the 2011 Plan of Finance for the following three
reasons. Costs of $340,000 have been included to investigate and incorporate environmentally
sustainable processes and practices components. These costs were identified for this project in
the 2011 Committed CIP #C800160. Secondly, a more detailed cost estimating process was
utilized increasing the direct and indirect construction costs by roughly $300,000. Thirdly, the
initial estimate was for a roof system with a 20 year design life, an additional $600,000 has been
included in the estimate range for roofing systems with a longer design life that more closely
matches the length of the lease. Additional analysis will be performed during the design process
to determine if the longer design life will provide the lowest cost of ownership to the Port.
Ultimately the roofing system with the lowest total cost of ownership will be selected.
In addition to the removal and replacement of the roofing system, the project provides an
opportunity to investigate and implement environmentally sustainable practices and processes as
part of the new roof systems. As the design develops, environmentally sustainable options will
be evaluated utilizing criteria identified in EX-15, that include total cost of ownership,
environmentally-sustainable development, conservation of resources and possible grant
reimbursement as a method of determining which sustainable elements will be included in the
final project. Potential sustainable elements may include; rainwater harvesting, passive solar
system, reduction in roof heat adsorption, and wind generation.