
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
July 20, 2011
Page 2 of 5
BACKGROUND:
By virtue of being located in the northwest corner of the continental United States, a high
number of originating departures are scheduled by the airlines to leave early in the morning to
reach the most frequented destinations at desirable times. Similarly, aircraft return to the Airport
at night to fuel and prepare again for the next day’s early morning flights. As a result of the high
number of morning departures, a disproportionately high number of passenger aircraft remain
overnight at the Airport than there are terminal gates available. Indeed, while the Airport has in
operation approximately 78 aircraft gates, roughly another 30 off-gate parking locations are
required each night to accommodate RON aircraft. Hardstand parking positions are needed to
accommodate these off-gate RON aircraft so that they are available for the morning peak traffic
demand. After the first wave of early departures from the terminal gates is complete, the off-gate
RON aircraft are moved to the vacant gates for a second wave of morning departures. Without
the ability to accommodate off-gate RON aircraft, airlines would have to park these aircraft at
another airport and fly them in for the early morning departures, which would be a costly and
inefficient proposition. In the absence of sufficient RON parking capacity, airlines are unable to
provide the optimal capacity for the identified local demand.
In August 2008, the Commission authorized 100% demolition design of the USPS Air Mail
Center facility and 15% design of hardstands to accommodate additional RON parking for
passenger aircraft. A memo to the Commission dated July 28, 2008, noted that between 2002
and 2007 the Airport experienced 17% passenger growth in air traffic. with a corresponding
increased demand for RON parking of passenger aircraft. The available hardstands decreased by
two positions (taxiway N and P stubs) when the third runway and associated taxiways were
activated in 2008. Since 2008, the Airport has experienced a slight decrease in passenger
volumes, but growth has been positive over the past year for both passengers and operations with
no increase in available RON parking positions.
Factors influencing the supply and demand of RON positions are difficult to manage and predict
as airline flight and aircraft maintenance schedules change frequently throughout the peak travel
season, and occasionally unscheduled or irregular operations also occur. Until now, Airport staff
has met RON demand but with increasing difficulty by managing more frequent parking and
towing of aircraft onto and off of Airport controlled common use gates and hardstands, including
the hardstands reserved for cargo aircraft. While agreements between airlines can be negotiated
to allow RON parking of another airline’s aircraft within the primary airline’s leased hardstand
area, Airport staff does not have sufficient control over these areas to guarantee the availability
of RON space when needed.
Additional RON parking positions are needed to meet the expected demand and to provide
flexibility to accommodate irregular schedules of both passenger and cargo aircraft. An in-depth
analysis by Airport staff, and consent from the airlines through the Majority in Interest approval
process, recommended the USPS Airmail Facility site for additional RON development at the
Airport. The Port Commission authorized termination of the lease with USPS and a capital
project for 100% demolition design and 15% hardstand design on August 26, 2008. Termination
of the lease was completed on February 15, 2010, for an actual buyout total of $4,972,045.45.