
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
July 19, 2011
Page 2 of 6
USACE noted that the risks associated with the dam would last up to five years. Subsequently,
the USACE have made modifications to the dam such that the risk of failure is about 1 in 60 this
winter. As a result, during the winter season storms, water may have to be released to the Green
River and threaten breach of the dikes. Should this occur, PSE facilities could be at risk of
damage/failure resulting in a loss of power to the Airport.
On October 15, 2009, a Declaration of Emergency was declared by the CEO and a project was
initiated to install temporary backup power in the event of power loss. By early December, all
nine generators and the attendant equipment were installed and were ready to activate if needed.
The system was never activated as PSE electrical power was maintained all winter. That system
was demobilized in April 2010.
On July 22, 2010, after reviewing the USACE assessment of the dam and the Green River dikes,
reviewing additional mitigation work performed by PSE, and studying weather forecasts for the
2010 to 2011 winter, the airlines understood the need to install the temporary backup power
system again that winter, as a precaution against power interruption due to flooding or other
hazards. In October 2010, the system was installed again, and in March 2011 was removed;
however, the site work and cabling remained for use again this season.
For the 2011 to 2012 winter, staff is attempting to have the system operational by November 1,
2011, the approximate start of seasonal heavy rains and winter season storms. This request is for
the expense funds needed in 2011 ($1,528,325) and in 2012 ($1,572,072) to install and lease the
equipment, purchase enough fuel to test the system, and run it for approximately eight hours.
This request does not include the cost of fuel to run the system for an extended period should
storm or dam situations warrant it. Those costs, if incurred, will be approximately $92,000 per
day of operation depending on cost of diesel fuel, however the fuel cost pales in comparison to
business disruption impacts if the airport is without power for an extended period of time.
The Port intends to use an existing indefinite duration/indefinite quantity (IDIQ) contract to
complete design requirements and provide construction support. The Port will competitively
procure the generators and ancillary equipment – this equipment will be the same rated capacities
as equipment for previous years. In addition the procurement contract will have options for
future years and also a purchase option if a later determination is made to construct a year-round
permanent facility rather than lease generators for a five month period as is planned again for this
storm season. We estimate the cost of equipment to be $1,951,293 for the 2011 to 2012 winter.
Through the competitive process, the Port will have the option to lease (or purchase) the
generators and ancillary equipment for 2011 to 2012, with an option to renew for four one-year
periods.
Port Construction Services (PCS) will be utilized again this year to self-perform work in
conjunction with a competitively procured major construction-project-specific, unit-price
contract. Airport maintenance staffing will be used to provide all switching, monitor installation
and testing, and operate the system when needed. The Port of Seattle will use an existing open-
order contract to procure the diesel fuel.
The Airport’s decision to install temporary backup power generation in 2009 also caused the
airlines to evaluate the effect a serious power outage from Green River flooding or from any