Item No: _____7e_supp________ Date of Meeting: __June 28, 2011__ RCF Construction June 3, 2011 May 4, 2011 RCF Construction RCF North Escalator Bank Finish Work RCF CSB Lobby Flooring Installation Progress BMF Bldg. - Tilt Panel Forming & Casting Excavating Slopes on B-Line 2 Rental Car Facility Program Contract - Status Summary Base Contract Amount Revised Additional Costs * In review ** Executed Unallocated Balance Billed to date (as of May.2011) Consolidated Rental Car Facility Total Construction Costs $224,837,739 $211,421,525 $1,526,668 $202,773,224 $7,081,179 $206,770,452 $5,953,159 $17,031,082 $13,879,211 $10,546,115 ($7,394,244) $7,297,715 $16,800,000 89,202 $8,640,600 $8,070,198 $8,644,612 Construction Contingency Summary Non Suspension Contract Changes Suspension Related Contract Changes $7,757,133 Off Site Roads Construction Contract Amount $7,627,485 Construction Contingency $1,087,000 $2,057,000 $247, 871 $7,627,485 $0 $4,182,569 1,735,330 $73,780 $1,039,187 $13,096,444 $0 $2,903,864 $10,000 $1,424,264 $0 Bus Maintenance Facility Construction Contract Amount $13,086,444 Construction Contingency $1,611,000 $176,736 NOTE: * updated as of May 9, 2011 ** includes costs in dispute for entitlement or quantum 3 4 Consolidated Rental Car Facility Program Costs as of 6/16/2011 Project 6/30/09 Budget 2/2/10 Authorization Approved Transfers/ Trends RCF $350,772,000 $350,772,000 $19,516,715 BMF $28,282,000 $28,282,000 ORI $19,542,000 MTI Buses Unallocated Contingency Total Pending Transfers/ Trends Remaining Contingency Expended to Date Forecast to complete $13,968,413 $7,757,133 $291,613,954 $351,102,000 ($1,890,000) $176,736 $1,424,264 $6,212,870 $26,382,000 $19,542,000 ($1,493,670) $247,871 $73,799 $8,979,822 $17,203,000 $3,383,000 $3,383,000 $0 $0 $338,300 $279,882 $3,383,000 $17,327,000 $16,000,000 ($4,911,269) $0 $219,897 $340 $12,415,731 $0 $0 $8,737,269 $150,000 $8,887,269 $0 $0 $419,306,000 $417,979,000 $19,959,045 $14,543,020 $18,700,662 $307,086,868 $410,485,731 5 6