Item No. 7c_Supp Date: June 14, 2011 Capital Improvement Projects First Quarter Report 2011 Commission Briefing Capital Improvement Projects Overall Status of Projects • 88 Total Projects in report • 48 Projects are within or ahead of target schedule and budget • 38 Projects have either target schedule or budget off • 2 Projects have both schedule and budget off Project Status Total CIPs Managed by CDD 100% 90% Project Distribution per Quarter 80% 70% 60% 50% 40% 30% 20% 10% 0% 1Q10 Report 2Q10 Report 3Q10 Report 4Q10 Report 1Q11 Report Both Schedule and Budget off 2 3 1 1 3 Either Budget or Schedule off 27 27 28 30 30 On Schedule/On Budget 39 43 45 42 41 AVIATION PROJECT SUMMARY • Three projects are behind schedule: - FIS Inspection Booths (1 month) - Unanticipated site access issues required a redesign. - Aircraft RON Parking (6 months) - RMM evaluation and development of a remediation plan. - S Sat Delta Sky Club (2 months) - Added scope and unanticipated existing conditions at roof level. • One project is forecasting an overrun: - S Sat Delta Sky Club (~$3.5M) - Additional scope changes. • One project is ahead of schedule: - Terminal Escalator Modernization (5 months) - Design-Build contract was executed in first quarter with accelerated date. AVIATION PROJECT SUMMARY, Cont. Cost of Construction Growth: - Connect C1 BHS to C88 BHS (12.99%) - The 12.99% growth on the project resulted from the request by Alaska to upgrade the C92 computers to mitigate issues with sorting the baggage and related interruptions to airline activities. • SEAPORT PROJECT SUMMARY One project is behind schedule:  T-5 Crane Cable Reels - delivery of materials has been delayed six months. REAL ESTATE PROJECT SUMMARY One project is behind schedule:  FT C15 HVAC Improvements - consultant schedule took longer than anticipated causing a delay of six weeks. CORPORATE PROJECT SUMMARY Two projects with new reportable schedule variances this quarter: - Business Continuity (6 months) - A small number of remaining components are dependent on the design of another project. - Ground Transportation Management (6 months) - The system design phase took longer than anticipated due to resource constraints and the resolution of system support issues.