Capital Improvement Projects
First Quarter Report 2011
Commission Briefing
Item No. 7c_Supp
Date: June 14, 2011
Capital Improvement Projects
Overall Status of Projects
88 Total Projects in report
48 Projects are within or ahead of target schedule and budget
38 Projects have either target schedule or budget off
2 Projects have both schedule and budget off
1Q10 Report 2Q10 Report 3Q10 Report 4Q10 Report 1Q11 Report
Both Schedule and Budget off
2 3 1 1 3
Either Budget or Schedule off
27 27 28 30 30
On Schedule/On Budget
39 43 45 42 41
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Project Distribution per Quarter
Project Status
Total CIPs Managed by CDD
AVIATION PROJECT SUMMARY
Three projects are behind schedule:
FIS Inspection Booths (1 month) Unanticipated site access
issues required a redesign.
Aircraft RON Parking (6 months) RMM evaluation and
development of a remediation plan.
S Sat Delta Sky Club (2 months) Added scope and
unanticipated existing conditions at roof level.
One project is forecasting an overrun:
S Sat Delta Sky Club (~$3.5M) Additional scope changes.
One project is ahead of schedule:
Terminal Escalator Modernization (5 months) Design-Build
contract was executed in first quarter with accelerated date.
AVIATION PROJECT SUMMARY, Cont.
Cost of Construction Growth:
Connect C1 BHS to C88 BHS (12.99%) - The 12.99% growth on the
project resulted from the request by Alaska to upgrade the C92
computers to mitigate issues with sorting the baggage and related
interruptions to airline activities.
SEAPORT PROJECT SUMMARY
One project is behind schedule:
T-5 Crane Cable Reels delivery of materials has been delayed six
months.
REAL ESTATE PROJECT SUMMARY
One project is behind schedule:
FT C15 HVAC Improvements consultant schedule took longer
than anticipated causing a delay of six weeks.
CORPORATE PROJECT SUMMARY
Two projects with new reportable schedule variances this quarter:
Business Continuity (6 months) A small number of remaining
components are dependent on the design of another project.
Ground Transportation Management (6 months) The system
design phase took longer than anticipated due to resource
constraints and the resolution of system support issues.