
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
June 3, 2011
Page 2 of 5
the economic environment and financing uncertainty in the bond market. In July 2010 the project
was reactivated at the 90% level, requiring that a design review be completed to ensure site
conditions had not changed and to coordinate with other ongoing projects. During review it
became apparent that scope needed to be changed to accommodate additional gates, as well as to
move some scope to other projects that were underway in an effort to minimize disruption to
airline operations. Two gates were added to the scope, along with a third 400 Hz motor generator
set for the South Satellite gates, and power centers had to be upgraded to provide additional
electrical capacity. The current project to provide pre-conditioned air to aircraft has taken
advantage of the available electrical capacity at these power centers. Due to the very long lead
time for 400 Hz motor generator sets, prepurchase by the Port is required to reduce the
construction duration.
The additional $3,498,000 is needed for the final design of the additional scope of work,
additional staff resources, and the purchase of the additional motor generator set. The new
project capital budget is $12,883,000.
PROJECT JUSTIFICATION:
Project Objectives:
Enable the Airport to gain more flexibility to maximize the use of each gate
Extend the service life of each gate through refurbishment of major components and systems
to increase reliability
Reduce the possibility of a carrier being assigned to a gate without the same amenities
Advance the Port’s goal of standardizing Port-provided amenities at all gates
Provide sufficient power at International Gates to support the next generation of large aircraft
PROJECT SCOPE OF WORK AND SCHEDULE:
Scope of Work:
The scope of work for this project includes the replacement of 400 Hz and potable water utilities
at 31 Airport owned gates. The Port will purchase and dispose of three airline owned 400 Hz
motor generator sets and prepurchase five new 400 Hz motor generator sets to provide adequate
power at all gates, including new generation wide body aircraft at the South Satellite. Design will
be completed by amending the existing sole source service agreement. Staff will return to the
Commission in September to request final authority to advertise for construction.
Schedule:
Design June - August 2011
Advertise for Equipment Purchase August 2011
Commission Authorization to Advertise September 2011
Advertise Construction Project October 2011
Award Equipment Contract October 2011
Equipment Manufacturing November 2011–April 2012
Notice to Proceed December 2011
Construction Complete December 2013