
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
May 27, 2011
Page 2 of 4
setting unseasonable weather conditions this spring, it was necessary to compress the paving work
to be done within conditions favorable to paving, resulting in shorter work windows and requiring
over-time hours to complete the work before opening of the cruise season. Both the unfavorable
wet weather and the need for overtime hours were not originally assumed in the project estimate.
These conditions all contributed to the additional construction costs.
These contributing factors can be mitigated by better controls and earlier communication of
potential cost overruns. Staff is currently working on deployment of a project delivery system that
will help define and manage all project costs. It will allow for the identification of all
commitments, which will be tracked to actual as reported through the Port’s financial systems. It
will also include tools to identify trends, and to forecast budgets. When deployed our new controls
system should reduce the potential for unforecasted cost overruns.
Construction is now complete and intersections/roadways are in use -- completed before the start
of the 2011 cruise season as scheduled. However, an additional $87,000 is necessary to cover these
unforeseen costs.
BACKGROUND AND JUSTIFICATION:
Roadway pavement at Terminal 91 adjacent to the east and west main terminal entrances and
main traffic intersections were in poor condition with a significant amount of surface breakage,
settlement, cracks and areas of pavement failure. This in turn created issues such as surface
water ponding and roadway operation/safety concerns. The pavement needed to be replaced
before additional pavement failures occurred and to enhance terminal roadway operation and
safety.
Staff obtained design funding approval on December 15, 2009 and construction funding approval
on September 28, 2010. A total of $895,000 was authorized by the Commission. Construction
started November, 2010 and the team coordinated closely with the Terminal 91 Water Main
Replacement Project team, Terminal Operations and our tenants to minimize disruptions to their
operations.
A significant amount of asphalt paving work occurred in March and April 2011. During the course
of construction within several large work areas, where existing pavement was designed to be
ground to a 2” depth and an overlay applied, the condition of the asphalt was determined to be
structurally unsound and that a full 4” depth replacement was needed. The affected areas were
significantly more than what was assumed during design. Also, in order to match grade of existing
paving and to ensure proper drainage, additional pavement replacement was required beyond
original design. Furthermore, weather conditions limited our ability to work and over-time hours
were required to meet the construction completion date. These items contributed to the additional
construction costs. Construction is now complete and roadways are in use.