TODAY’S BRIEFING FOR May 24, 2011
RCF GC/CM Construction Contract:
Construction Status Summary
ï‚· Construction progress is 92% complete.
ï‚· Construction costs are trending to be within authorized budget.
ï‚· An average of 180 construction workers are on site daily.
ï‚· Over 1,298,232 work hours have been expended on the project to date. Based on the dollars spent to
date, over 3,600 new jobs have been created due to this project since project work commenced in
2008 (using data from the 2009 UW study performed for AGC).
ï‚· Current construction waste recycled materials rate is 96.96%.
ï‚· Recordable Incident Rate (number of injuries per 100,000 work hours) for 2011 is 1.24. Overall
project RIR is 3.30, significantly below the statewide rate of 11.0. The project is nearing 3 years
without time lost on the job due to injuries.
Milestones Accomplished This Month
ï‚· Turnover date for the tenant spaces in the Customer Service Building has been met, and the areas
have been punch listed as of April 19, 2011.
ï‚· Customer Service Building roof is complete and punch listed.
ï‚· Coved architectural ceiling in the Customer Service Building is complete.
Work In Progress
ï‚· RCF Elevated Concrete Decks - Punch list work continues.
 Customer Service Building (CSB) – Coved architectural ceiling is complete. Bathroom fixture
installation is in progress. Lobby terrazzo installation is in progress as well. Back of house floor,
wall and ceiling finishes are well under way. Installation of doors commenced. Roof membrane
installation is complete and punch list has been issued.
ï‚· RCF Operational Floor Plates - Painting of the operational floor plate ceilings and waterproofing
work continues, weather permitting. Mechanical and electrical systems installation is in progress and
nearing completion on all levels in areas D, E and F. Floor plate sealant application has commenced.
Work on the core bathrooms is nearing completion.
ï‚· Seismic Joints - Installation of seismic joints in the main building areas, and in QTA-s is nearing
completion.
ï‚· Elevator and Escalator Equipment - Installation is nearing completion. Installation of escalator
cladding has commenced.
ï‚· QTA Progress - Installation of electrical and mechanical systems and wall framing are in progress in
QTAs 1, 2, 3 and 4 support buildings, with QTA-s 1 and 2 and 3nearing completion. Exterior
resinous flooring installation is essentially complete. Interior floor epoxy installation is in progress in
QTA-s #3 and #4.
 Car Wash Equipment – Installation is nearing completion.