
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
May 16, 2011
Page 2 of 6
total square footage of leased space. The airlines approved the original Delta Sky Club tenant
reimbursement project through a Majority In Interest (MII) vote in December 2010.
With Commission authorization, staff will finalize an adjustment to the current tenant
reimbursement agreement and add the additional 1,300 square feet to the existing lease.
BACKGROUND:
On March 23, 2010, the Commission approved $5.44 million of funding to reimburse Delta for
base building construction of a 6,800 square-foot airline lounge and for Port project support to
assist in building this facility on the roof of the South Satellite. Delta moved forward with
design of the project after Commission approval, but soon thereafter put the project on hold
before the design work was completed. Delta at that time was considering a proposal to move
their operation back to Concourse A from the South Satellite. After a brief delay, Delta decided
to commit to the South Satellite location and signed the Port’s tenant reimbursement agreement.
Delta was concurrently considering an expansion of the lounge footprint to accommodate their
anticipated growth as part of their location analysis.
Delta decided to add 1,300 square feet to their partially designed lounge, increasing the footprint
from 6,800 square feet to 8,100 square feet. The Port was only committed to costs associated
with the original scope, but the proposed change included additional shell construction that the
Port would typically pay for under the Tenant Reimbursement Policy AV-2. At Delta’s request,
and at their financial risk, they proceeded with this additional expansion work as a change order
to the project, with the understanding that the Port could not commit to additional compensation
for the lounge expansion unless approved by the Commission. Costs were provided to the Port
in late March 2011. Total costs are now anticipated to exceed the established budget for the
project, and are therefore part of this request for additional authorization.
In addition to the expansion scope, Delta also notified the Port of several change orders based on
unidentified project conditions as they prepared to submit their expanded lounge costs to the Port
in March. These necessary changes were identified as the tenant contractor investigated the
existing roof structure after construction began. Those change order costs further exceed the
established budget for this project and are also included in this request.
PROJECT SCOPE OF WORK AND SCHEDULE:
Expansion Scope of Work:
Additional 1,300 square feet of new building shell
Addition or expansion of existing building systems into the expanded building shell
Special inspection and commissioning of new Port infrastructure systems
Unidentified Project Conditions Scope of Work:
Resolve structural steel conflicts with existing or proposed infrastructure in the ceiling of
the South Satellite