COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
May 23, 2011
Page 3 of 7
clarification of positions and adjustment of rates. Amendment no. 4 increased the contract by
$185,666 to add scope and approved the use of overtime to complete the design to meet revised
FAA grant application deadlines. Total contract value is $2,197,230 ($1,794,577 for design and
$402,666 for construction support).
Stantec’s scope of work included designing utilities to each Preconditioned Air Unit at 73 gates.
The design required an extensive pipe distribution from the Central Mechanical Plant to each
terminal and then to each individual gate. After reviewing the alternate piping routes, which
included ramp-level and roof-top locations; the design team selected the roof-top route to
minimize construction impact to airline and tenant operations.
On May 11, 2010, the Commission authorized additional funding of $36,830,000 for the Port to
advertising and executing the construction contract. Bids were opened on July 15, 2010. The
contract was awarded on September 13, 2010. Notice to proceed was issued November 5, 2010.
As the general contractor and sub-contractor prepared submittals for approval of piping
fabrication, they suggested alternate pipe routings at ramp level for South Satellite, Concourse B
and Concourse C, to avoid obstructions, ease installation, and eliminate issues with roof-top
installation. The contractor’s proposed method of material delivery and installation significantly
reduced the impacts on operations. After reviewing the Contractor’s proposal, the Port agreed to
review the revised routing. Staff determined that the revised routing was feasible and would
minimize potential change orders by avoiding roof-top obstructions and other utilities, eliminate
utility shutdowns to concourse tenants, and minimize potential roof damage.
The contractor is ready to start shop fabrication of the piping and pipe supports. Amending the
contract with Stantec Consulting will allow the Port to support the contractor’s schedule.
The period of performance for the service agreement will not change. It is from July 29, 2010,
through January 30, 2013.
Staff is not requesting additional project funds for this amendment. Cost for project management
activities are below budget. However, staff may return to Commission later to request additional
funding to address potential change orders related to other aspects of the project.
PROJECT STATEMENT AND OBJECTIVES:
Project Statement:
Construct the PC Air system with an associated central plant including individual PC Air gate
units at all passenger loading bridges.
Project Objectives:
Provide a PC Air System that will accomplish the following:
Decrease the amount of energy used to heat and cool the aircraft.
Significantly reduce the amount of CO
2
and other air emissions produced.