BACKGROUND & PROJECT SCOPE OF WORK:
Completion of the SOA project at the RCF is required per the Consolidated Rental Car Facility
Lease Agreement between the Port and the rental car companies operating at the Airport. The
project is designed to accommodate three (3) Small Operators in the new RCF. During the
design of the RCF, it was not known how many Small Operators or how large of an area would
be required to accommodate the Small Operators. It was decided during the General
Contractor/Construction Manager (GC/CM) negotiations with Turner Construction that certain
portions of the SOA project integral to the construction of the building would be included in their
contract. The remaining scope consisting of installing kiosks for the SOA staff, electrical/data
communications infrastructure to support SOA operations, infrastructure for SOA signage, and
other related infrastructure systems to support SOA operations, is the subject of this
memorandum. This work was left to be designed and constructed by the Port to allow flexibility
in accommodating up to three future Small Operators. Since construction has been underway on
the RCF, the Port’s Business Development Department now has a better understanding that there
will be two Small Operators in the facility. The RCF design team is currently in the process of
developing the final design of the SOA project in accordance with the RCF lease agreement for
three (3) Small Operators. Since the build-out for the Small Operators represents costs that
would typically be paid by the tenant, the Port will fund these costs with the ADF (rather than
Customer Facility Charge revenues) and will establish and collect rent from the Small Operators
to recover these costs.
PROJECT STATEMENT/OBJECTIVES:
Project Statement:
Provide rental car operations space for up to three (3) Small Operators at the RCF.
Project Objectives:
Provide an effective and economical operational area for Small Operators.
Provide for a sustainable environment for Small Operators to maintain competiveness and be
successful.
Provide a level playing field for new Small Operator entrants
STRATEGIC OBJECTIVES:
This project supports the Port’s strategy to:
“Ensure Airport Vitality”
“Be a Catalyst for Regional Transportation Solutions,” and to
“Exhibit Environmental Stewardship Through Our Actions.”
The SOA project is part of the RCF program, which provides a long-term transportation solution
for the region and supports the Port’s Small Business initiatives by supporting a variety of rental
car operators at the Airport. As part of the Aviation Division’s demonstration project for
sustainable design, the design team also considered the total cost of ownership as part of
significant design decisions for the this project.