
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
April 22, 2011
Page 2 of 3
As required by RCW 53.19.060 and Resolution No. 3605, this memorandum also constitutes
notification to the Commission when the amended amount exceeds 50% of the original not to
exceed contract value. This memorandum will be placed on file for public inspection at the
Port’s bid desk.
BACKGROUND:
In April 2008, the Port of Seattle began the procurement process for design and construction
support services for the BMF project as a Category C contract. In July 2008, the Port of Seattle
executed a Professional Service Agreement with AJEM for $1,900,000. This contract was
executed prior to the issuance of Port Policy CPO-1; however, it includes the requirement for the
issuance of Service Directives in order to authorize work. In July 2009, the contract was
amended to add $350,000 for design and construction support services in support of the addition
of the compressed natural gas fueling facility to the BMF project. In June 2010 the contract was
amended to add $220,000 for design support to address required changes to the contract
specifications.
Construction support services were originally estimated and included in the original $1,900,000
Professional Service Agreement for the BMF project, and included in the $350,000 amendment
for the compressed natural gas fueling facility. These estimates for construction support services
totaled $440,000 and were based upon a range of assumptions that defined the overall scope of
work and level of effort before the project began the design phase.
At the completion of the design phase, the range of assumptions used to define the overall scope
of work and “level of effort” for the construction support services were reviewed. The overall
scope of work has increased since a greater number of submittals and coordination meetings are
now required, and a greater number of requests for information are anticipated, than was
previously assumed for the project. Given the changes in the Port’s standard operating
procedures, the “level of effort” assumptions for each task included in the scope of work has also
significantly increased. The total estimated cost for construction support services is now
$790,000 which is $350,000 greater than the original estimated budget.
An additional $100,000 is included in this request for a total increase of up to $450,000 in order
to provide contingency within the contract for the completion of construction support services,
the procurement and installation of furniture, fixtures and equipment, and for the completion of
the LEED© certification process post construction. Since this contract requires the issuance of
Service Directives in order to authorize work, these additional funds will not be authorized
unless required to support the BMF project.
The current contract value is $2,470,000, and with the execution of this amendment, the value of
the AJEM Agreement would be $2,920,000.
SCOPE OF WORK AND SCHEDULE:
The following major scope elements to be continued for completion of the BMF project include,
but are not limited to:
Responding to requests for information;
Reviewing project submittals;