included in the Seaport Small Project CIP. During the fourth quarter of 2010, the project was scoped,
and funding became available in the 2010 Small Project CIP due to cancelled and delayed projects.
Preliminary design work evaluated alternatives for increasing restroom capacity while minimizing
disruption to the terminal. The selected alternative retains the existing front lobby restrooms with access
from outside the building. New restrooms are built around the existing restrooms with access from
inside the building.
The preferred alternative was finalized in January 2011. The authorized project budget of $260,000 was
determined based on a construction cost estimate prepared by a consultant assuming a contractor would
do the work. The building permit was obtained on February 3. Construction work requires a minimum
of eight weeks assuming all materials are purchased and available. Cruise ships begin arriving at the
Smith Cove Cruise Terminal on May 7, 2011.
Schedule constraints did not allow sufficient time to put the project out to bid. During acquisition
planning, it was decided that Marine Maintenance crews would do the work with support from Port
Construction Services.
Despite construction challenges, the Restroom Expansion Project has remained on schedule. However,
the project is over budget.
PROJECT JUSTIFICATION:
The project is over budget due to a combination of the following factors:
The authorized project cost was based on a consultant’s construction cost estimate calculated at
the end of the preliminary design phase. At that time, we were assuming a contractor would be
performing the work.
Based on material costs only, the consultant grossly under-estimated costs. The consultant's total
estimated material cost was approximately $30,000. Actual material costs, including sales taxes,
are expected to be approximately $70,000. It is likely that the consultant's estimated labor costs
would also have been low if we had used a contractor.
The project drawings were of low quality. Marine Maintenance crews spent a lot of time
rectifying drawing errors and omissions. Examples include, but are not limited to: inadequate
space allotted in the plumbing walls; incorrect ADA dimensions; misrepresented vents and
sprinkler systems; and, specified plumbing fixtures not corresponding to the plumbing
infrastructure. If these drawings had gone out to bid, the resulting change orders would have
resulted in an even greater project cost.
The Marine Maintenance 2011 burden rate has had a large impact on the budget. Over $100,000
will be charged to the project in allocated overhead.
PROJECT SCHEDULE:
The new restrooms are nearing completion. The restrooms are expected to be operational before May 7,
2011.