
Management Letter – Review of the Port Capital Improvement Program Page 3
For the two change orders discussed above, Port management issued two separate cost
estimates in March 2009. The cost estimates were written within one week of each other
and totaled $293,000. One single event triggered the need for the change orders.
Specifically, during the drilling for the geo-piers installation, the contractor encountered
excessive obstructions. One change order was for $130,000 to remove the excessive
obstructions, and another for $163,000 for the contractor to use alternative method of
over-excavation or structural backfill repair on the disturbed sub-grade areas.
Because one common trigger (event) changed the scope of work, management should
have issued only one change order, and obtained commission approval for the total
amount of the change order. Writing two separate change orders, instead of one, has the
appearance of splitting change orders in order to avoid Commission approval. At the time,
any change order exceeding $200,000 required Commission approval
Recommendation
We recommend CPO management continue its current practices of training Port staff on
CPO policies and compliance with Port procedures.
Department Response
POS CM staff evaluates the merit of discrete issues or events that give rise to a change
order based on its individual circumstances. The issues of over-excavation to allow
geopier installation in Change Order 5 and the fundamental change in foundation type in
Change Order 9 were considered two discretely different issues that arose from a similar
condition of debris-laden soil conditions in February and March of 2009 respectively. One
required the contractor to remove obstructions whereas the other issue required a new
foundation type which had to be designed and drafted by the designer of record. POS CM
staff believed that while the causes of both change orders were the debris-laden soil,
these were two different changes required to solve the two issues. There was no intent to
split change orders and avoid Commission approval.
There will be instances where the Port will need to issue incremental change orders to
direct changed work as the scope of work is being fully defined to ensure that we satisfy
the RCW on prompt pay and to direct critical work in the field. Our current practice
requires email notifications to Port managers and directors for the cumulative value of the
change, in addition to the EX-2 signature authority limits. We will continue to review and
revise our current procedures to provide key accountabilities and transparency and
provide staff training and management oversight to ensure that CM staff understands and
complies with Port policies, procedures and expectations
.
2. Small Works Roster System
The Port utilizes the online Small Works Roster system to solicit contractors for Small Works
opportunities. The Port provides all registered contractors an equal opportunity to compete for a
contract.
We noted a deficiency in the design of the online Small Works system. The current system can
allow exclusions of otherwise eligible contractors from the bid solicitation. When there is a Small