of 2004 with Walker Parking for $100,000 to re-initiate the team, determine who from the original team
needed to be replaced and to develop the project manual the design team would operate by for the entire
life of the project. Under amended 3605 and CPO-1, staff would probably have executed a contract
for the full amount authorized in March 2001 and issued a Service Directive for $100,000.
Between March and October 2004 six amendments were issued, two specific for completing the concept
validation and detailed programming of the RCF, and four to design the Rental Car Improvements (RCI).
Under the amended 3605, these two amendments would have been issued as Service Directives.
Under amended 3605, the RCI project would not have been allowed to be amended to Walker’s
contract by staff, since the scope was not included within the original scope for soliciting the RCF
design team. Under SB 3274 and CPO-6, Commission might have determined that a new
competitive solicitation was not appropriate or cost-effective, allowing this out-of-scope
modification.
In April 2005, the Commission authorized the RCI project to expand rental car operations to the second
floor of the existing garage as a result of the delay in the RCF project, constrained on-site facilities (1
st
floor of garage) and excess garage capacity. In order to meet that project’s aggressive schedule, staff
received approval through the Decision Committee to amend Walker’s contract to design and support
construction of the MGI project using funding outside of the RCF project.
In November 2004, the Commission authorized funds to design the RCF and to procure the GC/CM
contractor. It is important to note the scope of the RCF now became the current program which included
the RCF, the Bus Maintenance Facility (BMF), the Off-Site Roadway Improvements (ORI), the Main
Terminal Improvements (MTI) and the purchase of buses. Under the amended 3605, the Commission
action would have included language to amend Walker Parking contract for the amount being
authorized and to serve as the 50% notification requirement. An amendment would have been
issued for the full authorized amount.
Between November 2004 and December 2006, five amendments were issued. During this time the RCF
project was stopped and restarted twice and staff was directed to slow the design as a result respectively
of obtaining legislation to collect Customer Facility Charges to fund the program, the decision of
Southwest Airlines to not move to King County Airport and the evaluation of the 3
rd
developer alternative
the Industry requested the Port consider. Under the amended 3605 all but one would have been issued
as Service Directives. Amendment 7 would not have been issued since it was for the RCI project.
In February 2007 the Commission authorized additional design and GC/CM pre-construction funds.
Under the amended 3605, the Commission action would have included language to amend the Walker
parking contract for the amount being authorized and to serve as the 50% notification requirement. An
amendment would have been issued for the full authorized amount. Between March 2007 and February of
2008, eight amendments were issued. Under the amended 3605 and CPO-1, all but two would have
been issued as Service Directives to complete the final design of the RCF and design development of
the ORI. Amendments 15 and 17 would not have been issued as the BMF project was not
considered within the scope of the original solicitation.
Later in 2008 the Central Procurement Office ruled the BMF could not be completed by Walker
Parking and a new competitive solicitation following 3605 was conducted. Arai Jackson was selected
as the new designer. During this period staff was directed to expedite final design of the RCF program,
the Industry and the Port rejected the 3
rd
party developer alternative, staff evaluated and the Industry and
Port rejected the Main Garage RCF alternatives and the Commission froze all capital projects.
In May 2008, the Commission authorized additional design funds and award of the GC/CM contract to
Turner Construction. Under the amended 3605, the Commission action would have included
language to amend the Walker parking contract for the amount being authorized and to serve as
the 50% notification requirement. An amendment would have been issued for the full authorized
amount. Between June 2008 and October 2008, six amendments were issued to support