Page 3 of 6
Milestones Accomplished This Month
ï‚· No major milestone completions,
Work In Progress
ï‚· Work is 95% complete on the north side of S 160th St. Sidewalk installation remains at 80%
complete and is weather dependent.
ï‚· Clearing activities at the south side of S. 160
th
Street is complete; TESC installed and storm drainage
installation underway and preparation for upcoming roadway improvements continues.
ï‚· Work on the new on-ramp to eastbound State Route (SR) 518 via the North Airport Expressway
continues on a weather dependent basis. The concrete SEW wall is complete and rebar and forming
work at the single slope barrier at the NAE elevation is underway.
ï‚· Qwest not yet scheduled to install fiber at SR 99.
ï‚· Consideration of additional potential locations of unknown conditions at A-Line (International
Boulevard, B-line (SR 518 off-ramp to SR99), C-line (SR 518 on Ramp) and SR 99 Bridge
potentially increases the cost impact to the $79,000 range.
ï‚· Work continues at SR99 Bridge with the seismic upgrades at the existing structure with foundation,
column, bolster and girder stop installations nearly complete. The girder installation traffic control
plan is tentatively approved for work scheduled to begin March 28, 201l.
ï‚· Weekly meetings with Port staff, Mid Mountain and Turner and WSDOT continue for coordination
and planning purposes as work progresses for both contractors.
Cost Status Summary
ï‚· Change Orders: 11 executed and 15 in review. A $960,000 Not-to-exceed change order Commission
Memo was approved on February 22, 2011 for unforeseen and unsuitable soils in preparation of the
upcoming road and bridge excavation work scheduled to begin in late March, early April.
Bus Maintenance Facility - Construction Contract
Construction Status Summary
ï‚· Overall project completion date is established at February 13, 2012.
ï‚· Construction progress is approximately 4%.
ï‚· Construction costs are trending to be within authorized budget.
ï‚· Contractor has begun utility installations and forming/reinforcing/placing site retaining walls.
Foundation submittals are approved for the main building and some pre-fabrication of footing forms
has begun. Contractor has completed TESC and Chitosan Enhanced Filtration System (CEFS)
installations and is maintaining/operating in accordance with best management practices (BMPs).
ï‚· Weekly meeting with Contractor continues to facilitate discussion on schedule and upcoming work
activities.
Milestones Accomplished this Month
 Contractor’s Baseline schedule was accepted on 3/7/11.
Cost Status Summary
ï‚· Three Construction Bulletins (CBs) issued and two Contractor proposals are in review. Three
additional Contractor initiated-change requests pending review. Summary: Change Orders: 0
executed 5 in review.