
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
March 18, 2011
Page 5 of 6
TRIPLE BOTTOM LINE SUMMARY:
This action links to the overall completion of the Third Runway Project, which was developed in
an environmentally responsible way and overall is a vital regional transportation facility that
supports economic growth in many ways.
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS:
Option 1 – Do Nothing. This option would result in the Port not being in compliance with
environmental permits and likely result in sanctions being issued by the environmental
regulatory agencies. The existing undersized Pond M would remain in place, potentially
allowing excessive flows to cause erosion in Miller Creek. Discharges from the SDS 6/7 Vault
would not meet current standards specified in the permits. This is not the recommended option.
Option 2 – Modify Pond M and install the SDS 6/7 control structure. This option would result in
the Port fulfilling environmental commitments for stormwater management and provide a
stormwater facility that meets current standards. This is the recommended option.
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST:
None.
PREVIOUS COMMISSION ACTION:
On August 1, 1996, the Commission adopted Port Resolution No. 3212, as Amended, approving
the Master Plan Update for Airport, including development of a new dependent air carrier
runway, and authorizing initial development work for the Runway project.
On May 27, 1997, the Commission authorized $587,362,000 for completion of the Runway
project to be completed by 2004.
On June 22, 1999, the Commission authorized an additional $186,000,000, increasing the total
authorization to $773,362,000. At that time, it was estimated permitting would be finalized by
December 1999 and the Runway project would be complete by fall 2006.
On June 24, 2003, the Commission was briefed on additional costs from delays, permit
conditions, market conditions, scope of project, and FAA requirements. At that time, the
Runway project was scheduled to be completed at the end of 2008.
On October 11, 2005, the Commission authorized an additional $125,000,000 increasing the total
authorization to $898,362,000.
On September 26, 2006, the Commission authorized an additional $219,594,000 increasing the
total authorization to $1,128,956,000.
On April 21, 2009, the Commission authorized the advertisement for construction bids for the
Lora Lake Demolition, Des Moines Nursery Mitigation and the Third Runway Stormwater Pond
Projects.
On July 28, 2009, the Commission authorized design for Miller Creek Relocation Revisions,
160
th
Street Culvert Removal, and Third Runway Environmental Mitigation at Seattle-Tacoma
International Airport.