
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
February 22, 2011
Page 2 of 8
project labor agreement will be applied to this project as a result of the safety and time-
sensitivity needs associated with working in the airfield restricted areas.
BACKGROUND:
In 2009, Airport staff conducted a visual survey of the non-runway pavement on the airfield, to
determine which pavement needed replacing, and in what sequence. It was determined that the
South Satellite work should be completed first, due to the deteriorating condition of the
pavement caused primarily by the design of the original 40 year old slot drain system, which is at
the end of its useful life. To that end, work in 2011 will focus on replacement of the slot drains
and the associated pavement around the South Satellite. Pavement joint seals will also be
replaced, to take advantage of the already closed gates.
The slot drain and adjacent concrete were originally installed in 1971 with an expected service
life of 20 years. Typical degradation of the concrete is occurring. In the areas adjacent to the slot
drains the concrete is degrading at an accelerated rate. Joint seal in the area has degraded and in
some cases is nonexistent.
The concrete, slot drain and joint seal work must occur in a phased, gate by gate, fashion to keep
the Satellite functional for our airline tenants. Advance acquisition and installation of temporary
common use passenger processing equipment is required in order to enable a more efficient shift
of airlines between gates to allow the work in the vicinity of respective gates to proceed.
The scope of work for concrete, slot drain and joint seal work includes temporary common
use podiums for flights displaced by this project. Gates S8 and S9, which do not have
common use equipment, will be used while other gates are not available. The temporary
common use podiums will allow flights to be shifted to gates that currently do not have common
use equipment and minimize impacts to the airlines and passengers. On September 28, 2010, the
Commission provided authorization to design, acquire equipment, and install the temporary
common use podiums. As the design progressed, it became apparent that the electrical and
communication connections were more challenging than anticipated and that the acquisition of
the equipment would cost approximately $178,000 more than anticipated. Therefore, additional
funds are included in this request to allow installation of the common use equipment.
This project is part of a multi-year program to replace some of the worst pavement and joint seal
on the airfield. The project will generally replace the most critical pavement first, but will
include other pavement sections when it makes sense, such as replacing aging pavement that still
have some service life remaining can avoid future operational impacts. The criticality and order
of the multi-year pavement replacement program may change over time, based on pavement
deterioration, operational impacts, and available funding. The 2011 project is anticipated to be
approximately $6,629,000, which includes the funds currently being requested. The overall
program amount for work from 2010 to 2015 is $30.8 million.
The majority of the water distribution system at the Airport is almost 40 years old. The system is
equipped with buried pipes and some strategically located valves so that portions of the system
can be isolated in the event of breaks, leaks, or tie-ins. However, certain valves do not work
properly or are inoperable and have reached the end of their life expectancy. Major, critical