
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
February 11, 2011
Page 2 of 8
This project is located on a former Superfund cleanup site (Lockheed Shipyard Upland Operable
Unit). EPA has required Lockheed to complete stormwater improvements; however the Port has
a pre-existing duty to maintain the cap. The Port and Lockheed propose to enter into an
agreement that clarifies their legal relationships for the construction of the Utility Infrastructure
Upgrade Project.
At the time of the June 22, 2010, Commission meeting, staff estimated the total project costs
would be approximately $6,700,000. Since then, EPA has mandated that construction storm
water be disposed off site. Total project costs is now increased by $505,000 to $7,205,000 to
address this requirement. If favorable weather condition is encountered, costs to address storm
water runoff could be drastically reduced.
In order to implement construction during periods of low rainfall and to meet aquatic area
construction requirements, the project is on a tight timeline. Staff is requesting Commission
approval for construction funding now, allowing initiation of the public bid process.
Construction is expected to be substantially completed by October 31, 2011, a one-month delay
from the schedule shared with the Commission on June 22, 2010. If the pending agreement is
not finalized by the time of selection of a contractor, the project will not be awarded, and
construction will likely be delayed until 2012.
ADDITIONAL BACKGROUND:
Terminal 10 is located on the west shoreline of Harbor Island, within the boundaries of the
Harbor Island Superfund area. The Port purchased the former shipyard site, now referred to as
Terminal 10 (T-10), from Lockheed Martin Corporation (Lockheed) in 1997 to provide land
necessary for implementation of the Terminal 18 (T-18) Redevelopment Project. Between 1998-
1999, Lockheed conducted a cleanup project at T-10 in compliance with Consent Decree No.
C94-1823 (the “Upland Remedial Action”), which consisted of excavating soils and installing
areas of asphalt cap to isolate remaining upland contaminated soils. Under the terms of the
purchase and sale contract, the Port agreed to (1) maintain the asphalt cap in compliance with the
Upland Remedial Action Consent Decree; (2) pay environmental costs arising from any
subsequent redevelopment of the property; (3) ensure that any improvements constructed on the
uplands would not diminish the effectiveness of the Uplands Remedial Action; and (4) conduct
no activities on the uplands that would contribute to increased costs of the Sediment Remedial
Action (see below). Lockheed retained responsibility for groundwater monitoring of the Upland
Remedial Action, and for the entirety of the Sediment Remedial Action.
In 2004, Lockheed conducted a cleanup of the aquatic lands adjacent to the property, in
compliance with a separate Consent Decree (the “Sediment Remedial Action”). This consisted
of removing approximately 3.4 acres of overwater creosote piling dock and platform structures,
approximately 2650 linear feet of vertical steel, concrete, and timber bulkheads, and excavation
of contaminated sediments, as required by EPA. In addition, a five feet thick aquatic area cap
was installed to isolate remaining contaminants from the West Waterway. Because the Sediment
Remedial Action was conducted on State-owned aquatic land, Lockheed obtained a Use