
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
February 22, 2011
Page 2 of 5
allowed the site to be used for the management of construction site stormwater associated with
Runway 16L reconstruction. Ecology’s water quality branch granted the Port a two-year
extension.
Following this extension, Port staff developed plans with the intent of constructing Pond M in
the summer of 2010. Included in those plans were provisions to install an outfall structure in the
SDS 6/7 stormwater vault. The Commission provided authorization for construction bid
advertisement as part of the Airfield Improvement Project-2 (AIP-2) on January 12, 2010.
Subsequent to that authorization, unforeseen site conditions, particularly unsuitable foundation
soils, were discovered by geotechnical investigations. These conditions necessitated further
analysis and design prior to obtaining a dam safety permit from the Ecology. The additional
analysis and design work, in addition to a restrictive construction schedule window set by
Ecology, necessitated separating the Pond M work from the 2010 contract. Ecology’s water
quality branch was notified of the additional design needs and extended the Third Runway’s
permit requirements for completing the stormwater facility until the fall of 2011. The
Commission authorized a one-year delay to the construction of Stormwater Detention Pond M on
May 24, 2010, in accordance with Section 4.2.3.3.(ii) of Resolution No. 3605. No additional
project funds are being requested as part of this authorization. The original budget for the 2010
AIP-2, per the January 12, 2010 authorization was $6,625,000. The estimated cost of the Pond
M modifications and SDS 6/7 outfall structure installation is $1,389,000. The additional analysis
and design work did not result in the estimated cost exceeding the budgeted amount for the work.
PROJECT JUSTIFICATION:
Pond M is one of several stormwater projects that were required to fulfill Third Runway
environmental permit obligations. Completion of Pond M stormwater detention facility will
satisfy the outstanding permit requirements and in doing so provide flow control and additional
water quality treatment for approximately 160 acres of Airport surfaces draining to Miller Creek.
The existing SDS 6/7 vault has been constructed with an outlet that provides temporary flow
control but does not meet current standards. A new control structure will provide the required
hydraulic controls.
Project Objectives:
Convert the existing construction Stormwater Pond M and expand it to a permanent stormwater
detention facility and install a permanent control structure in the SDS 6/7 vault the Airport.
PROJECT SCOPE OF WORK AND SCHEDULE:
Scope of Work:
The existing construction stormwater pond will be expanded through the excavation and
construction of a two-celled facility with a final detention capacity of approximately 26 acre-feet.
Each cell will be formed by an earthen berm, constructed to meet dam safety permit
requirements. Underlying soils determined to be unsuitable for the embankment foundation will
be removed. Conveyance piping spillways, hydraulic control structures, and outfall pipes to
receiving waters will be installed. A heavy plastic liner will be anchored to the inner berm
slopes and netting will be fitted above both cells to reduce the pond’s open water attraction to
wildlife. The SDS 6/7 control structure work will entail installing a baffle wall in an existing