
Page 2 of 5
Installation of electrical and mechanical systems and wall framing are in progress in QTAs 1, 2, 3 and
4 support buildings. Exterior resinous flooring installation is in progress in QTA’s 1, 2 and 3. CMU
wall installation is ongoing for QTA #4 back of house spaces.
Car wash equipment is being installed in QTA 2.
South architectural stair installation is in progress.
Installation of architectural metal panels on level 6 (penthouse mechanical and clerestory) is
complete. Metal panel installation commenced on electrical shafts and Level 5 support buildings.
Temporary erosion & sediment controls are being maintained. The site is in good condition and
ready for the ongoing winter weather.
Contractor Schedule
RCF Substantial Completion date is November 15, 2011. Current progress update shows a negative
twenty nine day float in the project schedule, with the critical path running through the QTA power-
up and commissioning. This is a 6 day time loss from what was reported on the last update. The Port
continues to review the progress schedule for sequencing and logic ties to validate the schedule status,
and is working diligently with Turner staff to improve on the status of activities and overall
completion date. In addition, staff has authorized selective overtime for tasks related to drying-in of
the building and for critical path activities.
Cost Status Summary
See Cost Status Summary Table in PowerPoint Supplement page 3 for current cost information and page
4 for the trending of Construction Contingency costs over time.
Subcontractor Bids – closed
Risk Reserve – 91 approvals have been issued, and 12 in review.
2% MACC (Maximum Allowable Construction Costs) Contingency – 99 Change Orders executed
and 21 in review.
Negotiated Support Services – 41 approvals issued.
Conforming Design Development Allowance – closed
Anticipated Scope Allowance – closed
Non-Suspension Related Contract Changes – 448 Change Orders executed, and 111 in review. Port
staff is currently trending approximately $8,000,000 in potential claims from the GCCM and a major
Subcontractor.
Suspension Related Contract Changes – 58 Change Orders have been written. One last claim relates
to the unsupported cost previously rejected by the Port from one subcontractor.
Off-Site Roadway Improvements - Construction Contract
Construction Status Summary
Construction progress is 35% complete.
Construction costs are trending to exceed originally budgeted amount by approximately $140k
primarily due to the significantly larger quantity of anticipated unsuitable or contaminated soils on
WSDOT property. The construction contingency budget will be revised pending the upcoming
Commission approval of the budget transfer from the unallocated program contingency to the project
contingency.
16 construction workers on site daily.