
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
February 11, 2011
Page 2 of 7
pursuing an aggressive schedule in which they propose to occupy gates on Concourse D by early
2012. Due to this realignment, a number of airlines are scheduled to relocate operations to gates
with PLBs that are currently owned and maintained by another airline. This project would
replace airline-owned PLBs with Port-owned PLBs, simplifying operational and maintenance
concerns.
In order to facilitate this relocation schedule, the new PLB work at Concourse D needs to be
expedited. We therefore request a single authorization at this time for the advertisement and
execution of a major construction contract for new PLBs for Gates D1 through D5 only.
Because they are not under the same time constraints, we will return to the Commission to
request authorization to advertise and execute the remaining PLB major construction contract for
the replacement and refurbishment work on Concourse B, Concourse D (Gates D7, D8 and D10)
and the North Satellite after the completion of design.
BACKGROUND:
In the current Signatory Lease and Operating Agreement there is provision for a One-Time
Airline Reallocation allowing the Airport to reassign airline operations areas for better utilization
of the existing facility. The Airport has issued a notice of intent to exercise the One-Time
Airline Reallocation to support airline consolidation, maximize operational efficiency, and meet
the Port and airlines’ mutual interest in deferring significant capital expansion costs.
A consequence of the reallocation is that several airlines will be relocating their gate operations
to gates with PLBs that are currently owned and maintained by other airlines. For example,
American Airlines, Frontier Airlines, and JetBlue Airways are slated to use gates with PLBs
presently owned by Alaska Airlines.
Decisions related to which bridges should be replaced versus purchased and refurbished will be
made following detailed mechanical inspections. This authorization request seeks a single
Commission approval action for a time critical portion of the project, the replacement of five
PLBs on Concourse D at Gates D1-D5, that will expedite completion of this portion of the
project ahead of the relocation of new airlines to this concourse. The design of non-time critical
PLBs elsewhere on Concourse D, Concourse B, and the North Satellite are within this
authorization, however the advertisement and construction work for these bridges will return to
Commission to seek authorization at a later date.
The airport currently has a total of 74 PLBs. The Airport currently owns 52. 48 of the 52 PLB’s
are manufactured or supported by one manufacturer named John Bean Technologies (JBT)
Corporation. The airport is standardizing on JBT bridges over time to lower operating costs,
maintain warrantees, minimize parts inventory, streamline training of Airport maintenance staff,
and simplify operator training for both airline employees and their contracted ramp workers. As
a result any replacement PLB’s will be procured from JBT. The Commission was notified of
this sole source procurement strategy on July 9
th
2010. The current contract with JBT for