ITEM NO: ___6a Supp 1 DATE OF MEETING: 02/08/2011 Potential Port Contribution to the City of Auburn's M Street Grade Separation Project Working with Partners Port contribution to FAST project: • Continues Port commitment to FAST Corridor Partners • Fills funding gap POS FAST Corridor Investment Lead Agency Project Year CN POS Total Project Investment Investment Auburn 3rd St. SW Grade Separation 1999 $ 1,250 $ 31,500 Tukwila S. 180th St. Grade Separation 1999 $ 250 $ 23,300 WSDOT SR-519 P 1: Atlantic Overpass 2003 $ 7,100 $ 109,300 WSDOT SR-519 P 2: West-Bound Freeway Connection & Royal Brougham 2009 $ 5,600 $ 74,400 Seattle Duwamish ITS 2009 $ 500 $ 9,100 POS East Marginal Way Grade Separation 2009 $ 14,212 $ 49,000 Kent S. 228th St Grade Separation P 1 & 2 2009 $ 1,200 $ 46,100 Seattle Spokane St Viaduct 2009 3,400 168,500 Auburn M St Grade Separation 2012 $ 771.4 $ 22,785 $ 34,283 $ 553,985 TOTAL FAST ($ in thousands) POS Interest • Support longer, more frequent trains on the Stampede Pass rail line • Reduce freight delays on M Street • Reduce conflicts among modes • Enhance freight mobility • Improve safety and traffic flow Interlocal Agreement • Port contribution for construction • Tied to: • Benefit to the Port • Stamped Channelization Plan contained in ILA • Port collaboration on any design changes affecting Port benefit Funding Request M Street Grade Separation Project $771,400 Port Staff Resources and Expenses $2,500 Net Project Cost $773,900