TODAY’S BRIEFING FOR January 25, 2011
RCF GC/CM Construction Contract:
Construction Status Summary
ï‚· Construction progress is 82% complete.
ï‚· Construction costs are trending to be within authorized budget.
ï‚· 240 construction workers on site daily. There are currently three Helmets to Hardhats apprentice
workers on the project.
ï‚· Over 1,106,241 work hours have been expended on the project to date. Based on the dollars spent to
date, over 2,900 new jobs have been created due to this project since project work commenced in
2008 (using data from the 2009 UW study performed for AGC).
ï‚· Over 88,500 cy of concrete have been placed project wide.
ï‚· Current construction waste recycled materials rate is 97.39%.
ï‚· Recordable Incident Rate (number of injuries per 100,000 work hours) for 2010 is 4.07. Overall
project RIR is 3.25, significantly below the statewide rate of 11.0.
ï‚·
Milestones Accomplished This Month
ï‚· Installation of all elevated concrete decks is complete.
ï‚· Tower Crane #4 has been removed. No tower cranes remain on the project.
ï‚· Mechanical/Electrical/Plumbing Building Information Modeling (BIM) for the facility is complete
Installation of the steel frame to support the art mesh is complete on both helices.
ï‚· Painting of the CSB canopy is complete.
Work In Progress
ï‚· Elevated concrete deck punch list work is in progress.
ï‚· Customer Service Building (CSB) roof membrane installation is nearly complete. Installation of
electrical/mechanical/plumbing components continues. Customer service building curtain wall
system installation is complete, with the exception of trim and parapet coping. Curtainwall
insulation is 50% complete. Framing of the CSB walls and ceilings is approximately 60% complete.
Tile installation is complete in the north CSB restroom, and in progress in the south CSB restroom.
ï‚· Painting of the operational floor plate ceilings is in progress.
ï‚· Waterproofing work continues. Topping slab placement continues on Level 5.
ï‚· Installation of seismic joints in the main building areas A, B and C and in QTA-s #3 and #4 is
approximately 80% complete.
ï‚· Mechanical and electrical systems installation is in progress on all levels. Medium voltage cable
installation is in progress.
ï‚· Terrazzo installation is in progress in the north and south core family restrooms.
ï‚· Elevator and escalator equipment installation is in progress. All north elevator cabs have been
installed. North and south escalator installation is approximately 90% complete.
ï‚· Installation of electrical and mechanical systems, wall framing, and window glazing is in progress in
QTAs 1, 2, 3 and 4 support buildings. Exterior resinous flooring installation commenced in QTA’s 1,
2 and 3. Canopy steel and roof installation is complete in all QTAs. CMU wall installation is
ongoing for QTA #4 back of house spaces.
ï‚· Car wash equipment is being installed in QTAs 1 and 2.
ï‚· Installation of north and south architectural stairs is in progress.
Item No.: 7a_attach
Date of Meeting: January 25, 2011