COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
January 18, 2011
Page 2 of 6
inform a future project design team of project scope and programming elements and allow for an
efficient and cost effective design development process. In order to perform the pre-design
effort, a service directive to a previously executed terminal development strategy campus
planning services IDIQ will be executed in the amount of $385,000, with an additional $90,000
in Port project management and soft costs, bringing the total request to $475,000.00.
Another element of this authorization will allow execution of a project specific Service
Agreement for design services for the FIS Improvements Phase 1 project. A competitive process
will be used to select the best qualified entity to perform these design services. The estimated
not-to-exceed cost for the contract is $3,500,000. This authorization will only authorize the
execution of the contract. Service Directives for design work will be issued authorizing the
consultant to perform a specified scope of work only after staff has received authorization and
funding for the project in accordance with Port policies and procedures.
BACKGROUND:
The FIS facility at the Airport has been located at the South Satellite since its construction in the
early 1970’s. It is located within the building and provides a means to maintain separation
between international arriving passengers and other travelers until the international arriving
passengers have cleared the customs and immigration screening processes. The facility was
expanded once in the mid-1980s but today it is too small for the volume of international traffic
arriving at peak times. Growth in international passengers using the FIS at Sea-Tac increased by
approximately 8.8% over 2009, and is expected to continue to grow. In order to accommodate
this growth, which is important to the region’s economy, facility improvements are necessary.
PROJECT JUSTIFICATION:
This project will provide critically needed additional capacity for international arriving flights
and necessary asset renewal for the Airport’s 40 year old FIS facility. The FIS facility operation
is currently over capacity even when all scheduled flights arrive on time. When flights are off
schedule resulting in overlapping flight arrivals, congestion is extreme, and from time to time
results in two conditions which are costly and unacceptable to airlines: (1) lack of space to queue
waiting passengers results in their being held on-board the inbound aircraft which can delay the
outbound service; and (2) prolonged wait and process times cause connecting passengers to miss
their domestic flight out of Sea-Tac. Additional international arrivals during the peak will only
exacerbate this situation.
PROJECT SCOPE OF WORK AND SCHEDULE:
Scope of Work:
The first phase of this project will make targeted improvements to several capacity pinchpoints
in the FIS facility: primary immigration inspection, baggage claim, secondary customs/
agriculture inspection, and security checkpoint screening. A second phase will be necessary in