PORT OF SEATTLE
MEMORANDUM
COMMISSION AGENDA STAFF BRIEFING
Item No.
7a
Date of Meeting
October 27, 2009
DATE: October 16, 2009
TO: Tay Yoshitani, Chief Executive Officer
FROM: Michael Ehl, Director Airport Operations
George England, Program Leader, Project Management Group
Janice Zahn, Assistant Director Engineering Construction Services
SUBJECT: Monthly Briefing Update on the Consolidated Rental Car Facility (RCF) Program
At the Commission’s request, staff will brief the Commission on the project’s progress at every regular
Commission meeting held at Seattle-Tacoma International Airport.
The Commission presentation will focus on the following project topics:
Current Progress
Schedule
RCF GC/CM Main Construction Contract
o Status Summary
o Change Orders
Risk Factors
Other Significant Developments
Future Commission Actions