Scope of work: 1) Increase the size of the 8 footings between gridlines M through R/23
through 26 at the RCF and extend the footings at the North Helix to provide additional
structural support where the Helix ties into the RCF. 2) Modify the electrical equipment
pads to fit with the Owner Furnished Electrical Equipment.
Justification: 1) The bearing pressure of the existing soils under slabs and footings was
not adequate to transfer building loads. 2) The electrical pads for the owner supplied
equipment must adequately support the selected equipment.
Consequences of not proceeding: 1) The footings would not provide the required
structural support. 2) The electrical equipment would not be adequately supported on
required equipments pads.
FINANCIAL ANALYSIS:
Funds to pay for this change order are part of the project contingency funds that were included in
previously approved authorizations of $419,306,000.00. No additional project funds are being
requested as a result of this change order.
CONTRACT INFORMATION:
The following information relates to the contract and competitive award:
Contract award date: May 30, 2008
Original period of performance: May 30, 2008 to April 1, 2011
Previous contract extensions: 0 Days
Contract extension this change order: 0 Days
Current Contract Completion Date: April 1, 2011
Original contract amount: $224,837,739.00
Previous Change Order Nos. 001 – 101: $4,405,835.00
Current contract amount $229,243,574.00
This request, Change Order No. 0102 $302,885.00
Revised contract amount: $229,546,459.00