
COMMISSION AGENDA
T. Yoshitani, Chief Executive Officer
September 11, 2009September 11, 2009September 10, 2009
Page 2 of 3
contractor to work overtime on selective construction activities to accelerate the critical path
work and help mitigate the schedule impact and associated costs. This Change Order includes
the direct costs of the unsuitable/contaminated soil issue along with selective Port directed
overtime and a 10% contingency. A separate CO may be necessary to address any time impacts
or indirect costs that cannot be fully mitigated.
CHANGE ORDER DESCRIPTION AND JUSTIFICATION:
The following information relates to the pending change order scope and cost:
Change Order No. 094
Scope of work: Remove soil identified by the Geotechnical Engineer as unsuitable
underlying soil for the new construction and dispose of in accordance with state
regulatory requirements. Also remove soil identified to be contaminated with petroleum
products. Replace the excavated unsuitable and contaminated soil materials with new
native and imported structural fill. Work to be performed on a force account (time and
materials) basis. Selective overtime as directed by the Resident Engineer of critical path
work to mitigate schedule impact. Selective potholing as directed by the Resident
Engineer.
Justification: The existing soils under slabs and footings must be suitable to carry and
transfer the building loads. Existing site soil has been identified by the Geotechnical
Engineer of record as being unable to meet the structural requirements and must be
removed and replaced with materials that will need the structural requirements. Types of
unsuitable soils being discovered on the site include soft soils, tree stumps, organic
debris, residential tanks, buried trash and existing construction debris. The soil material
in the excavation which contains petroleum contamination must also be properly
disposed of offsite.
Consequences of not proceeding: Proceeding with construction over unsuitable soil
would result in unacceptable settlement of footings and cracks in slabs on grade and
could result in structural failure. The contaminated soil must be properly disposed of
offsite to meet our regulatory requirements.
FINANCIAL ANALYSIS:
Funds to pay for this change order are part of the project contingency funds that were included in
previously approved authorizations of $419,306,000.00. No additional project funds are being
requested as a result of this change order.
CONTRACT INFORMATION: The following information relates to the contract and
competitive award:
Contract award date: May 30, 2008
Original period of performance: May 30, 2008 to April 1, 2011