
PORT OF SEATTLE
MEMORANDUM
DATE: July 27, 2009
TO: Tay Yoshitani, Chief Executive Officer
FROM: Melinda Miller, Director, Portfolio Management
Tim Leonard, Capital Project Manager
SUBJECT: The completion of the South Wall reconstruction at Fishermen’s Terminal
(CIP 800136)
ACTION REQUESTED
Authorization for the Chief Executive Officer to proceed with permitting, design, and project
management to be performed for the completion of the South Wall reconstruction at Fishermen’s
Terminal (FT) in the amount of $980,000.
SYNOPSIS
The Real Estate Division requests approval for permitting, design, and project management
funding in the amount of $980,000 for the reconstruction of the final remaining section of the
original South Wall seawall at FT which has exceeded its service life and is at risk of structural
failure. The design, permitting, and project management will be performed by Port staff with the
exception of geotechnical and diving services which are estimated to cost approximately
$100,000. All design and permitting costs will be paid out of the $5,000,000 budgeted in the
2009 Draft Plan of Finance for this project under CIP C800136. Commission authorization for
construction funding will be sought upon completion of the engineering design and final
construction estimate.
BACKGROUND
The South Wall at Fishermen’s Terminal (FT) was originally constructed in 1914 and currently
separates the facility’s southern uplands from the harbor. A structural condition survey and
evaluation of FT, performed in 1999 by Reid Middleton engineers, determined that the
submerged timber relieving platform component had exceeded its service life and was at risk of
structural failure. This finding was primarily based on the severe dilapidation that has occurred
in the connectors holding the relieving platform together and the increased loads being placed
upon it by subsequent overlying wharf construction as well as the facility’s current operations.
The majority of the South Wall was reconstructed in 2003-2005 as a major works capital
improvement project. The only portion of the original timber relieving platform still remaining
is approximately 160 feet in length and located at the east end of the bulkhead that fronts the
parcel currently leased by Fishing Vessel Owners (FVO). Replacement of this section of the
seawall has been delayed due to various factors: The unavoidable disruption to FVO’s business