COMMISSION AGENDA
T. Yoshitani, Chief Executive Officer
August 3, 2009
Page 2 of 2
as part of this project. It was suggested by both the Designer of Record and the
contractor that a more superior finish would be achieved if the fabrication of the column
covers began after the finish floor height was established with the completion of the
flooring operations. The contractor agreed that this activity could be done at a later time
with no additional cost to the project; however additional days would be needed to extend
the contract date so that the fabrication of the column covers could wait until after the
finish floor was completed. It was determined that an additional 61 calendar days would
be required to complete this work. We are requesting Change Order Number 010 be
issued for these remaining days.
Consequences of not proceeding: While the column covers could have been
manufactured prior to the installation of the finished floor, the best results would be
achieved with this method.
FINANCIAL ANALYSIS: This is a no-cost change order.
CONTRACT INFORMATION: The following information relates to the contract and
competitive award:
Contract award date: August 07, 2008
Original period of performance: August 07, 2008 to April 06, 2009
Previous contract extensions: 60 Days
Current Contract Completion Date: June 5, 2009
Contract extension this change order: 61 Days
Revised Contract Completion Date: August 05, 2009
Original contract amount: $918,000.00
Previous Change Order Nos. 001 – 009: $193,950.00
Current contract amount $1,111,950.00
This request, Change Order No. 010 $0.00
Revised contract amount: $1,111,950.00