Briefing on Proposed Completion of
Fishermen’s Terminal South Wall Reconstruction
(Project No. 104132)
ITEM NO: 7b_Supp
DATE OF
MEETING: July 28, 2009
2
Briefing on Proposed Completion of Fishermen’s Terminal South Wall Reconstruction (Project No. 104132)
Site Plan
Previously completed South Wall
Reconstruction
Proposed South Wall
Reconstruction
3
Briefing on Proposed Completion of Fishermen’s Terminal South Wall Reconstruction (Project No. 104132)
Existing Typical Section
Briefing on Proposed Completion of Fishermen’s Terminal South Wall Reconstruction (Project No. 104132)
4
Existing Fishermen’s Terminal South Wall
Relieving Platform Connectors
(Pen is shown for size comparison)
5
Briefing on Proposed Completion of Fishermen’s Terminal South Wall Reconstruction (Project No. 104132)
Replacement Typical Sections
6
Briefing on Proposed Completion of Fishermen’s Terminal South Wall Reconstruction (Project No. 104132)
Existing FT Shipyard Marine Rail System
7
Briefing on Proposed Completion of Fishermen’s Terminal South Wall Reconstruction (Project No. 104132)
2003-2005 South Wall Construction Photos
8
Briefing on Proposed Completion of Fishermen’s Terminal South Wall Reconstruction (Project No. 104132)
2003-2005 South Wall Construction Photos
9
Briefing on Proposed Completion of Fishermen’s Terminal South Wall Reconstruction (Project No. 104132)
2003-2005 South Wall Construction Photos
10
Briefing on Proposed Completion of Fishermen’s Terminal South Wall Reconstruction (Project No. 104132)
Proposed South Wall Reconstruction Completion
Project Key Points
Final section of South Wall to be reconstructed is
approximately 160 feet in length
Existing shipyard marine rail system and infrastructure in
project area to be retained
$5,000,000 preliminary estimated project cost
Permitting and design funding approval will be requested
in August 2009
Construction funding approval will be requested in
spring/summer 2010
Construction to begin fall 2010
Construction to be completed by summer 2011