Briefing on Proposed Completion of Fishermen’s Terminal South Wall Reconstruction (Project No. 104132)
Proposed South Wall Reconstruction Completion
Project Key Points
•Final section of South Wall to be reconstructed is
approximately 160 feet in length
•Existing shipyard marine rail system and infrastructure in
project area to be retained
•$5,000,000 preliminary estimated project cost
•Permitting and design funding approval will be requested
in August 2009
•Construction funding approval will be requested in
spring/summer 2010
•Construction to begin fall 2010
•Construction to be completed by summer 2011