COMMISSION AGENDA
T. Yoshitani, Chief Executive Officer
July 2, 2009
Page 2 of 2
CHANGE ORDER DESCRIPTION AND JUSTIFICATION: The following information
relates to the pending change order scope and cost:
Change Order No. 002
• Scope of work: The original contract completion date was March 30, 2008. This was a
POS/Siemens negotiated contract under the State of Washington Energy Conservation
program (Interagency Agency Agreement (IAA) dated February 16, 2001. The initial
VFD manufacturer suspended deliveries on their equipment for 6 months in November
2007. The contractor found replacement equipment for this project from another
manufacturer that the POS deemed acceptable. These VFD’s did not arrive until after the
contract scheduled completion date. This precipitated delays in receipt of O&M manuals,
testing, adjusting, and balancing and the final commission reports. Substantial
Completion was achieved on August 15, 2008.
• Justification: This delay was caused by a supplier suspending delivery of VFD
components. As a result, the contractor could not perform per original schedule. There
were no Liquidated Damages included in this negotiated contract.
• Consequences of not proceeding: The project documentation would be incomplete to
provide justification for the contractor exceeding the contract completion date.
FINANCIAL ANALYSIS:
This is a non-compensatory Change Order.
CONTRACT INFORMATION: The following information relates to the contract and
competitive award:
CONTRACT TIME:
Contract Award date: April 30, 2007
Original period of performance April 30, 2007 to March 30, 2008
Original Contract Completion date March 30, 2008
Previous contract extensions 0 Days
Previous Contract Completion Date March 30, 2008
This request Change Order No. 002 138 days
Final Contract Completion Date August 15, 2008
CONTRACT PRICE:
Original Contract amount: $2,770,025.00
Previous Change Order No. 001 $15,581.00
Current Contract Amount $2,785,606.00
This Change Order No. 002 $0.00
Final Contract Amount $2,785,606.00