
COMMISSION AGENDA
T. Yoshitani, Chief Executive Officer
April 9, 2009
Page 5 of 5
On October 24, 1995, the Commission authorized $3,628,000 for the NPDES permit process for
the IWS including sampling and testing, engineering support, coordination with WDOE, design
and construction of interim improvements and thirty percent design of Lagoons No. 1 and No. 2
improvements and other miscellaneous improvements.
On June 10, 1997, the Commission authorized $350,000 to create snowmelt runoff facilities to
comply with the requirements of the NPDES permit.
On July 9, 1999, the Commission authorized $8,372,000 for sampling and testing, engineering
support, coordination with WDOE, design and construction of Lagoon No. 1 and No. 2
improvements, and other miscellaneous improvements, and thirty percent design of Lagoon No.
3 expansion.
Phase 1 Capital Improvement Program Authorizations
August 24, 1999, the Commission authorized $19,000,000 for the expansion of Lagoon No. 3 to
seventy two (72) million gallons and IWS piping within South 154
th
Street.
On July 9, 2002, the Commission authorized $500,000 for Industrial Wastewater System
Upgrade Phase IVA on a project-wide basis, for a total estimated cost of $19,391,000.
Phase 2 Capital Improvement Program Authorizations
On September 12, 2000, the Commission authorized $600,000 for preliminary design work on a
project-wide basis to optimize the ability to meet the requirements of the proposed Engineering
Report and the current NPDES permit.
On September 25, 2001, the Commission authorized $509,000 for construction of the section of
the AKART pipeline within International Boulevard (State Route 99). This was a portion of the
authorization request for utility improvements within International Boulevard.
On March 26, 2002, the Commission authorized $1,500,000 for the design work to meet the
AKART requirements for the IWS. The design includes piping, a pump station, treatment plant
improvements to segregate flows and a connection to the King County Renton Treatment Plant
for treatment of the high BOD IWS flow after pre-treatment at the Airport’s Industrial
Wastewater Treatment Plant and other miscellaneous improvements.
On November 11, 2003, the Commission authorized $19,173,000 for the Industrial Wastewater
System Upgrade Project.