COMMISSION AGENDA
T. Yoshitani, Chief Executive Officer
March 16, 2009
Page 2 of 4
order to complete the transaction of this document for the Commission authorization on
December 13, 2005 (Item 7b), corresponding amendments to the Base Lease, Leaseback and
Subordination, Nondisturbance and Novation Agreement are required. The December 13, 2005,
commission memo inadvertently failed to mention the need for Port Commission approval to
amend these documents. Port staff now requests Commission authorization for the execution of
the Second Amendment to the Base Lease, Leaseback, and Subordination, Nondisturbance and
Novation, agreements. These amendments for the three agreements are required because the
Terminal 18 leased area was reduced by approximately 0.67 acres requiring an updated legal
description. All elements of the December 13, 2005, authorized lease amendment have been
implemented.
A copy of the previous commission action on December 13, 2005, the proposed Third
Amendment to the Terminal 18 lease(signed by SSAT), and the proposed amendments to the
Base Lease, Leaseback and Subordination, Nondisturbance and Novation Agreement are
attached hereto.
The proposed Third Amendment to Terminal 18 lease, Second Amendment to the Leaseback,
and the Second Amendment to Base Lease require MBIA and Bond Trustee review and approval
before they can take effect.
MAJOR ELEMENTS OF PROPOSED AMENDMENTS:
The major elements of the previously approved lease amendment and the proposed amendments
to the Base Lease and the Leaseback are as follows:
1) Revise the legal description, lease lines and acreage of the Site area.
a. Adjustment of final lease line
b. Reduction in acreage by 0.67 acres as result of longshore parking on city right of way,
which therefore could not be fenced and controlled by SSAT.
c. Relocation of Kinder Morgan Energy Partners, a Port tenant, from the center berth area
to the north berth area resulting in decrease of acreage from 1.5 to 0.9 acres.
2) Memorialize the GATX pipeline relocation.
3) Address the applicability of the Drop Dead Date.
4) Document the Port’s commitment to undertake certain improvements at the Site.
5) Clarify Lessee’s maintenance obligations.