
COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
March 17, 2009
Page 3
PROJECT SCOPE OF WORK AND SCHEDULE
This project includes 100% design and permitting for the drainage improvements and
a pavement overlay necessary to prepare the site for use as temporary drayage vehicle
storage for trucks directly related to movement of cargo to and from the Port
terminals and potentially for use of T10 as cargo support area, uses consistent with
previously established uses and the IG/1 zoning at the site.
The design criteria and permits will meet state, local, and federal construction permit
requirements, construction requirements for a site adjacent to an active Superfund
listed site as well as environmental obligations under existing consent decrees and the
purchase and sale agreement.
Treatment of the surface runoff from the site will be designed to meet Basic
Treatment and High-Use Water Quality Standards established in 2005 by Department
of Ecology (DOE) Storm water Management Manual for Western Washington and
the City of Seattle Stormwater Drainage Code.
In March 2008, when Commission approved $530,000 for design and permitting,
staff estimated construction would be completed in 12-15 months—June 2009. Two
issues have impacted the schedule and budget:
1. At the time, the plan was to either use in-house Engineering to complete the
design or use an Open-Order Service Agreement. In-house Engineering staff was
assigned T25, a higher priority project, and staff determined use of the existing
open-orders was not appropriate. A Category 3 selection process began in early
April 2008, and the Service agreement was executed on November 10, 2008.
2. The original design assumed use of an existing 8-inch outfall until a new 24-inch
outfall could be permitted. It was assumed that permitting review for the outfall
would negatively impact the schedule and a phased approach to permitting the
outfall later was chosen. However, when the 30% design plan was shared with
interested Agencies, issues concerning construction on the superfund site,
maintaining the environmental cap, and installing a new outfall were positively
addressed leading to the conclusion to pursue the outfall design and permitting
concurrently with the upland improvements. The current plan recommends
including design and permitting of outfall, adding approximately 6 months to the
100% design and permitting schedule. In addition, the existing service agreement
with the designer did not include engineering and permit support for the 24-inch
outfall and an amendment is proposed to increase the Service Agreement from
$412,413 to approximately $505,000.
The original design and permitting budget was based on preliminary work completed
in 2007 and mistakenly did not include all the necessary Engineering and
Environmental support. The design estimate only included budget to complete the
design and permitting phase of the project using Port of Seattle Resources. The