detention and water quality that improves fish habitat and improves the ability for further
development within the Airport and the adjacent communities.
BACKGROUND:
The Comprehensive Stormwater Management Program (CSMP) was initiated in June 2002 in
response to permit conditions associated with the airport’s Master Plan Update. Numerous
stormwater facilities were designed and constructed to meet regulatory requirements and are
currently operational. The stormwater program has now moved into its Adaptive Management
phase under which additional or upgraded stormwater facilities will be implemented to meet new
regulatory conditions or to resolve other stormwater problems not previously anticipated. This
project is part of the Adaptive Management phase.
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS:
Previous Commission funding actions on CIP 102030 Comprehensive Stormwater Management
Plan include:
On June 11, 2002, the Commission authorized $1,000,000 to conduct preliminary studies
and finalize program definition and planning for a new Comprehensive Stormwater
Management Program, CIP 102030.
On March 11, 2003, the Commission authorized $9,354,000, which included: an
additional $4,125,000 for continuation of CIP 102030 Comprehensive Stormwater
Management Program Plan and Definition; $3,731,000 for initiating CIP 102108 Drives
Connection to IWS Project; $668,000 for initiating CIP 102109 Stormwater Pollution
Prevention Project; and $830,000 for initiating CIP 102146 Low Flow Pilot Program.
On February 10, 2004, the Commission authorized $10,000,000 for continuation of CIP
102030, Comprehensive Stormwater Management Program Plan and Definition.
On May 5, 2005, the Commission authorized $14,981,000 for continuation of CIP
102030, Comprehensive Stormwater Management Program Plan and Definition.
On October 25, 2005, the Commission authorized $12,408,000 for continuation of CIP
102030, Comprehensive Stormwater Management Program Plan and Definition.
On April 11, 2006, the Commission authorized an additional cost of $36,208,000 for
continuation of CIP 102030, Comprehensive Stormwater Management Program Plan and
Definition. Funding for Adaptive Management phase stormwater projects was authorized
by this action.