PORT OF SEATTLE
MEMORANDUM
COMMISSION AGENDA POLICY AND STAFF BRIEFING
Item No.
6a
Date of Meeting
February 10, 2009
DATE: January 28, 2009
TO: Tay Yoshitani, Chief Executive Officer
FROM: Fred Chou, Capital Project Manager
Ticson Mach, Capital Project Manager
SUBJECT: Terminal 30 and Terminal 91 Project Construction Field Progress
BACKGROUND
On November 13, 2007, Commission approved monthly briefings on the project’s progress.
On July 22, 2008, Commission requested more frequent briefings on the project’s progress.
Staff will provide an update at every regular Commission meeting.
BRIEFING OUTLINE
The Commission presentation will focus on the following topics associated with the current
progress of the project:
Overview of the construction activities
Work completed to date
Next Steps