PORT OF SEATTLE
MEMORANDUM
DATE: January 27, 2009
TO: Tay Yoshitani, Chief Executive Officer
FROM: Ralph Graves, Managing Director, Capital Development Division
SUBJECT: Change Orders #652 and #653 for the C-1 Baggage Handling System project
Contract MC-0310928
ACTION REQUESTED: This memorandum requests Commission approval to issue Change
Orders #652 and #653 for project closeout of the C-1 Baggage Handling System project in the
estimated net amount of $1,750,104 by reallocating previously authorized project contingency;
therefore at no additional cost to the project.
SYNOPSIS: Airline operational restrictions and regulatory agency requirements have
significantly impacted the schedule for the C-1 Baggage Handling System project. On June 24,
2008, Commission approved Change Order #614 which directed contract work after June 30,
2008 be performed and paid for on a Time and Material (T&M) basis. Two change orders are
required to fund the remainder of the T&M work to close out the project. The change orders are
estimated at a Not-To-Exceed total of $1,750,104. By using previously approved project
contingency dollars, no additional project funds are required for these change orders.
CHANGE ORDER DESCRIPTION AND JUSTIFICATION: The following information
relates to the pending change order scope and cost:
Change order #652 & #653
Scope of work: Reconciliation of Change Orders Nos. #634 through #639 for time and
material craft labor and management/supervision work performed up to December 2008.
Justification: Reconciliation change orders are required to establish the final amount for
this work.
Consequences of not proceeding: Port would not be in compliance with contract
requirements.